CASE 6.1
Advantage Energy Technology Data Center Migration*—Part
A
Brian Smith, network administrator at Advanced Energy
Technology (AET), has been given the responsibility of implementing
the migration of a large data center to a new office location.
Careful planning is needed because AET operates in the highly
competitive petroleum industry. AET is one of five national
software companies that provide an accounting and business
management package for oil jobbers and gasoline distributors. A few
years ago, AET jumped into the “application service provider”
world. Their large data center provides clients with remote access
to AET’s complete suite of application software systems.
Traditionally, one of AET’s primary competitive advantages has been
the company’s trademark IT reliability. Due to the complexity of
this project, Brian will have to use a parallel method of
implementation. Although this will increase project costs, a
parallel approach is essential if reliability is not to be
compromised.
Currently, AET’s data center is located on the second floor of
a renovated old bank building in downtown Corvallis, Oregon. The
company is moving to a new, one-level building located in the
recently developed industrial complex at the Corvallis
International Airport. On February 1, Brian is formally assigned
the task by the Vice President of Operations, Dan Whitmore, with
the following guidelines:
· From start to finish, it is anticipated the entire project
will take three to four months to complete.
· It is essential that AET’s 235 clients suffer no
downtime.
Whitmore advises Brian to come back to the Executive Committee
on February 15, with a presentation on the scope of the project
that includes costs, “first-cut” timeline, and proposed project
team members.
Brian had some preliminary discussions with some of AET’s
managers and directors from each of the functional departments and
then arranged for a full-day scope Page 203meeting on February 4
with a few of the managers and technical representatives from
operations, systems, facilities, and applications. The scope team
determined the following:
· Three to four months is a feasible project timeline and
first-cut cost estimate is $80,000–$90,000 (this includes the
infrastructure upgrade of the new site).
· Critical to the “no-downtime” requirement is the need to
completely rely on AET’s remote disaster recovery “hot” site for
full functionality.
· Brian will serve as project manager of a team consisting of
one team member each from facilities, operations/systems,
operations/telecommunications, systems & applications, and
customer service.
Brian’s Executive Committee report was positively received
and, after a few modifications and recommendations, he was formally
charged with responsibility for the project. Brian recruited his
team and scheduled their first team meeting (March 1) as the
initial task of his project planning process.
Once the initial meeting is conducted Brian can hire the
contractors to renovate the new data center. During this time Brian
will figure out how to design the network. Brian estimates that
screening and hiring a contractor will take about one week and that
the network design will take about two weeks. The new center
requires a new ventilation system. The manufacturer’s requirements
include an ambient temperature of 67 degrees to keep all of the
data servers running at optimal speeds. The ventilation system has
a lead time of three weeks. Brian will also need to order new racks
to hold the servers, switches, and other network devices. The racks
have a two-week delivery time.
The data center supervisor requested that Brian replace all of
the old power supplies and data cables. Brian will need to order
these as well. Because Brian has a great relationship with the
vendor, they guarantee that it will take only one week lead time
for the power supplies and the data cables. Once the new
ventilation system and racks arrive, Brian can begin installing
them. It will take one week to install the ventilation system and
three weeks to install the racks. The renovation of the new data
center can begin as soon as the contractors have been hired. The
contractors tell Brian that construction will take 20 days. Once
the construction begins and after Brian installs the ventilation
system and racks, the city inspector must approve the construction
of the raised floor.
The city inspector will take two days to approve the
infrastructure. After the city inspection and after the new power
supplies and cables have arrived, Brian can install the power
supplies and run the cables. Brian estimates that it will take five
days to install the power supplies and one week to run all of the
data cables. Before Brian can assign an actual date for taking the
network off line and switching to the hot remote site, he must get
approval from each of the functional units (“Switchover Approval”).
Meetings with each of the functional units will require one week.
During this time he can initiate a power check to ensure that each
of the racks has sufficient voltage. This will require only one
day.
Upon completion of the power check, he can take one week to
install his test servers. The test servers will test all of the
primary network functions and act as a safeguard before the network
is taken off line. The batteries must be charged, ventilation
installed, and test servers up and running before management can be
assured that the new infrastructure is safe, which will take two
days. Then they will sign off the Primary Systems check, taking one
day of intense meetings. They will also set an official date for
the network move.
Page 204
Brian is happy that everything has gone well thus far and is
convinced that the move will go just as smoothly. Now that an
official date is set, the network will be shut down for a day.
Brian must move all of the network components to the new data
center. Brian will do the move over the weekend—two days—when user
traffic is at low point.
ASSIGNMENT
1. Generate a priority matrix for AET’s system move.
2. Develop a WBS for Brian’s project. Include duration (days)
and predecessors.
3. Using a project planning tool, generate a network diagram
for this project.
Note: Base your plan on the following guidelines: eight-hour
days, five-day weeks except for when Brian moves the network
components over a weekend, no holiday breaks, March 1, 2010, is the
project start date. Ordering Ventilation System, New Racks, and
Power Supplies/Cables takes only one actual day of work. The
remaining days are the time necessary for the vendors to fill and
ship the order to Brian. So use Finish to Start lags here. Assume
that five days after the start of the Renovation of the Data Center
that the raised floor will be ready for inspection (a
Start-to-Start lag).
Expert Answer
This question hasn't been answered
ABOUT