Question

In: Accounting

1. The cost-allocation system Choice Hotels has been using allocates over 90 percent of overhead costs...

1. The cost-allocation system Choice Hotels has been using allocates over 90 percent of overhead costs to the Standard Guest Room and the Junior Suite, because over 90 percent of the models produced were one of these two models. How much overhead was allocated to each of the three models last year? Discuss why this might not be an accurate way to assign overhead costs to products.

2. How would the use of more than one cost pool improve Choice Hotels’ cost allocation?

3. Choice Hotels' production manager proposes allocating overhead by direct labor hours instead, since the different models require different amounts of labor. How much overhead would be allocated to each guest room (per unit and in total) using this method? Show all supporting calculations.

Choice Hotels Sales, Production, and Cost Information

Room Type Standard Guest Room Junior Suite Presidential Suite Type Cost
Volume 150 110 25 Depreciation $3,200,000
Price $140,000 $240,000 $1,050,000 Maintenance $1,800,000
Unit costs Purchasing $320,000
Direct materials $30,000 $92,000 $310,000 Inspection $850,000
Direct labor $54,000 $85,000 $640,000 Indirect materials $490,000
Manufacturing $30,000 $30,000 $30,000 Supervision $1,700,000
overhead Supplies $190,000
Total unit cost $114,000 $207,000 $980,000 Total manufacturing overhead cost $8,550,000
Unit gross profit $26,000 $33,000 $70,000 Note: Manufacturing overhead costs are fixed. They do not vary with the volume of manufacturing activity.
Direct labor hours 1,200 1,300 5,940
Rate per hour $45.00 $65.38 $107.74

Solutions

Expert Solution

1.

Particulars Standard Guest Room Junior Suite Presidential Suite Total
Volume 150 110 25 285
Volume in % 53% 39% 9% 100%
Manufacturing O/D Cost $                4,500,000.00 $ 3,300,000.00 $            750,000.00 $ 8,550,000.00

As mentioned in given case,
The Manufacturing overhead costs are fixed. They do not vary with the volume.
The allocation of overheads should not be based on volume because it not directly associated with how much models produced.
So, It is not an accurate way to assign overhead costs to products.

2.

Cost pool means grouping of costs incurred on a particular activity.
The manufacturing overheads are associated with activities that grenerates it.
So, for determining correct overhead absorption rate, it is important to divide cost pools with correct cost drivers.
If there is only one cost pool, then there will be difficulties in selecting one correct cost driver as there may be diffenent kind of cost activities which generate the cost.
Use of more than one cost pool help to determine correct overhead apsorption rate. In such case, cost pool can be divided by correct and more relevant cost driver.

3.

Particulars Standard Guest Room Junior Suite Presidential Suite Total
Volume in units (A) 150 110 25 285
Direct Labour Hours (B) 1200 1300 5940 8440
Manucaturing o/d Cost (D) [B x C) $ 1,215,639.81 $ 1,316,943.13 $ 6,017,417.06 $ 8,550,000.00
Allocation rate per hour (C) $ 1,013.03
(Total Overhead / Total Hours)
Manucaturing o/d Cost per unit (D / A) $ 8,104.27 $ 11,972.21 $ 240,696.68

Related Solutions

What are the difficulties in determining appropriate cost allocation of a firms overhead costs?
What are the difficulties in determining appropriate cost allocation of a firms overhead costs?
1) Why is overhead allocation important? 2) Why do we need to compute overhead allocation using...
1) Why is overhead allocation important? 2) Why do we need to compute overhead allocation using either the traditional method or ABC? In other words, why can't we just take our total overhead for the current period and divide it by the total number of units produced to get overhead per unit.
13. Hogan’s Ltd uses a job order cost system and allocates manufacturing overhead to orders on...
13. Hogan’s Ltd uses a job order cost system and allocates manufacturing overhead to orders on the basis of direct labour cost. The predetermined overhead rates for the year are 200% for Department A and 50% for Department B. Job# 23, started and completed during the year, had the following costs (note: some of the data below is incomplete) : Department A B Direct materials $25,000 $5,000 Direct labour ? 30,000 Manufacturing Overhead 40,000 ?
X Company uses a plantwide overhead allocation system, with direct labor cost as the cost driver....
X Company uses a plantwide overhead allocation system, with direct labor cost as the cost driver. Budgeted overhead for the year is $867,000. The following annual budgeted and actual information is available for the only three products that it produces - X, Y, Z: X Y Z Units of production 1,000 33,000 3,100 Direct labor hours per unit 8 4 3 Direct labor wage rate $17.00 $24.00 $26.00 How much overhead was allocated to Product Z [round the overhead rate...
Cost Accounting Ltd manufactures three products. The company allocates overhead costs as a rate per total...
Cost Accounting Ltd manufactures three products. The company allocates overhead costs as a rate per total direct labour hour. The following cost driver values have been identified: Machine hours / unit Production units Percentage of expert work Number of orders packed Labour hours Alpha 0.70 5 000 30% 4 1 200 Beta 0.30 3 500 20% 8 800 Gamma 0.50 8 000 50% 23 1 500 An analysis of the manufacturing overhead cost for the period shows the following: Activities...
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Budgeted:       Overhead      $343,000       Machine hours      88,000       Direct labor hours      9,800 Actual:       Overhead      $342,200       Machine hours      85,800       Direct labor hours       9,580       Prime cost      $1,464,700       Number of units      180,000 Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $fill in the...
XYZ Company is using job costing system. The allocation base for overhead is number of machine...
XYZ Company is using job costing system. The allocation base for overhead is number of machine hours. The company uses normal costing to compute the overhead allocation rate. The following data are available for 2017 year: Estimated total overhead cost                               $270,000 Estimated total number of machine-hours           200,000 Actual total overhead cost                                     $290,000 Actual total number of machine-hours                 220,000             Job 630 used 14, 000 machine hours.             The company had job 630 and other jobs during the year....
Assigning manufacturing overhead cost to activity pools is referred to as first-stage allocation because costs are...
Assigning manufacturing overhead cost to activity pools is referred to as first-stage allocation because costs are assigned first to the activity pools before being assigned to a. cost objects. b. activity objects. c. activity drivers. d. cost drivers. Omer Limited produces and sells electronic sound equipment. The company has production capacity of 20,000 units and currently production schedule is for 18,000 units. Each unit has a selling price of $25, variable product cost of $15, and variable selling cost of...
Mannon Company’s accountant exclaimed, “Our cost accounting system allocates overhead based on direct labour hours, but...
Mannon Company’s accountant exclaimed, “Our cost accounting system allocates overhead based on direct labour hours, but our overheads cost appear to be more related to setup activities than to the use of direct labour. It seems as though our costing system allocates too much cost to large batches of product and not enough cost to small batches. Explain what she means.
Q 4 Abdulkarim Company is using job costing system. The allocation base for overhead is number...
Q 4 Abdulkarim Company is using job costing system. The allocation base for overhead is number of machine hours. The company uses normal costing to compute the overhead allocation rate. The following data are available for 2017 year: Estimated total overhead cost                                 $270,000 Estimated total number of machine-hours                 200,000 Actual total overhead cost                                       $290,000 Actual total number of machine-hours                      220,000             Job 630 used 14, 000 machine hours.             The company had job 630 and other jobs during...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT