A classification count of vehicles over a 40 day period follows: Austroads Class Vehicle Count Class...

  1. A classification count of vehicles over a 40 day period follows:

Austroads Class

Vehicle Count

Class 1

25,500

Class 3

1,000

Class 4

2,000

Class 9

1,500

  1. What is average daily traffic in terms of vehicles?                                      
  2. What is the percentage of heavy vehicles?                                                
  3. What is average HVAG/HV (NHVAG) using the typical heavy vehicle axle configurations for vehicle classes 3, 4 and 9?                                                                              
  4. What are the heavy vehicle axle group proportions?                                  
  1. A two-way 2 lane rural road (1 lane in each direction) has an estimated 1st year of design AADT of 15,000 vehicles. Given the following data, what is the design traffic loading in terms of ESA?     

Design period = 30 years; Annual growth rate = 3%; %HV = 15% NHAVG = 2.8 HVAG/HV; Average ESA/HVAG = 0.95

Solutions

Expert Solution

so we are given the vehicle count and so can calculate the total count over 40 days

So 30000 vehicles are counted over 40 days

So average daily traffic = 30000/40 = 750 vehicles/day

The Class suggests something about he type of the vehicle. I have listed it as follows

So assume that HEAVY VEHICLES = Class3, Class4 and Class 9 only we have

% of heavy vehicles = 4500/30000 = .15 = 15%

NHVAG = # of heavy axle vehicle groups per heavy vehicle including

SADT - Single Axle Dual Tire

TAST - Tandem Axle Single Tire

TADT - Tandem Axle Dual Tire

QADT - Quad Axle Dual Tire

For our data we have the following Heavy Vehicle Axle Group Proportions

NHVAG = average number of axle groups per heavy vehicle in a single day = (50 + 100 + 112.5)/(25+50+37.5) = 2.333

Typically FHWA classification for axles and vehicle classes shows as follows

-------------------------------------------------------------------------------------------------------------------------------------------------------------

The Design Traffic Loading can be calculated using the formula

NDT = 365 * AADT * Directional Factor * Lane Distribution Factor * (%Heavy Vehicles in decimals) * GRN * NHVAG * ESA/HVAG

where

AADT = average daily traffic = 750

Directional Factor = take higher direction or .5 if 50-50

Lane Distibution Factor - in our case only one lane so this is 1

% heavy vehicles- we already calculated to be 15%

GRN = growh factor = [{(1 + Growth Rate) ^ Design life } - 1]/ Growth Rate

= (1.0330 - 1)/0.03 = 47.575

so NDT = 365 *750 * 1 * 1 * .15 * 47.575 * 2.8 * .95 = 5196439 ESAL's


Related Solutions

Over a very long period of time, a sheriff determines the mean vehicle speed on a...
Over a very long period of time, a sheriff determines the mean vehicle speed on a road is 67 miles per hour, the standard deviation is 3 miles per hour. Treat this as the population, not a sample. If the speed limit is 60 miles per hour, what percentage of the vehicles exceed the speed limit? The sheriff cracks down on speeders. His deputies ignore any vehicles going less than 63 mph, and issue warnings to those going between 63...
Roy services (Oil Change) vehicles in his garage. His lubricants cost him $40 per vehicle. His...
Roy services (Oil Change) vehicles in his garage. His lubricants cost him $40 per vehicle. His wages are $120 per hour. He spends 20 minutes per vehicle. His garage rent is $600 per month. He charges $140 to service each vehicle. His Total Fixed cost is a. $400 b. $600 c. $720 d. $680
The average temperatures (°F) for an 8-day period are: 32,35,34,36,48,43,42, and 40. If the area has...
The average temperatures (°F) for an 8-day period are: 32,35,34,36,48,43,42, and 40. If the area has an initial SWE of 2.46 in, K=0.06in/deg-day, and a runoff coefficient of CR = 0.5, plot the estimated daily runoff (in) from the watershed and determine the total melt and runoff for the 8-day period.
The average temperatures (°F) for an 8-day period are: 32,35,34,36,48,43,42, and 40. If the area has...
The average temperatures (°F) for an 8-day period are: 32,35,34,36,48,43,42, and 40. If the area has an initial SWE of 2.46 in, K=0.06in/deg-day, and a runoff coefficient of CR = 0.5, plot the estimated daily runoff (in) from the watershed and determine the total melt and runoff for the 8-day period.
Over a period of 30 or 40 years, what is your estimate of how much of...
Over a period of 30 or 40 years, what is your estimate of how much of the change in economic output is due to the growth of potential GDP and how much is due to episodes of recession and economic upswings?
Freight car loadings over an 18-week period at a busy port are as follows:
  Freight car loadings over an 18-week period at a busy port are as follows: Week Tons loaded 1 220 2 245 3 280 4 275 5 300 6 310 7 350 8 360 9 400 10 380 11 420 12 450 13 460 14 475 15 500 16 510 17 525 18 541 The port manager wants build a model to forecast the loads for the remainder of the year. a. Which variable is the dependent/response variable? b. Which...
Famous Farm's payables deferral period (PDP) is 40 days (on a 365-day basis), accounts payable are...
Famous Farm's payables deferral period (PDP) is 40 days (on a 365-day basis), accounts payable are $120 million, and its balance sheet shows inventory of $208 million. What is the inventory turnover ratio?
1. (40 marks) Tim has preferences over consumption in period 0 and 1 of the form...
1. Tim has preferences over consumption in period 0 and 1 of the form U(x, y) = xy, where x and y are Tim’s consumption in period 0 and 1 respectively. He has $15,000 in the bank now and is trying to decide between two different investment opportunities, A and B. A: invest $10,000 in period 0 and receive $20,000 in period 1. B: invest $2,000 in period 0 and receive $6,000 in period 1. a. If Tim can borrow...
Over a three day period a clothing store sold the following number of shirts: 51, 65,...
Over a three day period a clothing store sold the following number of shirts: 51, 65, and 44. Over the same period the clothing store had 3, 6, and 1 sales staff working on the shop floor. Answer the following questions: Enter your final answers in the boxes below. Show ALL working by uploading your handwritten working for this question to Laulima Dropbox within 15 minutes of completing your exam. Correct answers without working shown will not receive full credit....
Over a 18 day period, daily measurements of silver yield from a mine us taken. The...
Over a 18 day period, daily measurements of silver yield from a mine us taken. The company has an original goal of the 60th percentile being more than 50 tons. From the 18 days, 8 days yielded less than 50 tons. No day yielded exactly 50 tons. Test to see if the company’s goal is upheld. (a) State the hypothesis for testing this claim. (b) Explain and show what test statistic you're using and how to get the p-value (c)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT