Question

In: Finance

NPV Your division is considering two projects with the following cash flows (in millions): 0 1...

NPV

Your division is considering two projects with the following cash flows (in millions):

0 1 2 3
Project A -$20 $5 $9 $12
Project B -$13 $8 $7 $3


  1. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
    Project A    $   million
    Project B    $   million

    What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
    Project A    $   million
    Project B    $   million

    What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55.
    Project A    $   million
    Project B    $   million

  2. What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places.
    Project A   %
    Project B   %

    What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places.
    Project A   %
    Project B   %

    What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places.
    Project A   %
    Project B   %

Solutions

Expert Solution

a

Project A
Discount rate 5.000%
Year 0 1 2 3
Cash flow stream -20 5 9 12
Discounting factor 1.000 1.050 1.103 1.158
Discounted cash flows project -20.000 4.762 8.163 10.366
NPV = Sum of discounted cash flows
NPV Project A = 3.29
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 5.000%
Year 0 1 2 3
Cash flow stream -13 8 7 3
Discounting factor 1.000 1.050 1.103 1.158
Discounted cash flows project -13.000 7.619 6.349 2.592
NPV = Sum of discounted cash flows
NPV Project B = 3.56
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 10.000%
Year 0 1 2 3
Cash flow stream -13 8 7 3
Discounting factor 1.000 1.100 1.210 1.331
Discounted cash flows project -13.000 7.273 5.785 2.254
NPV = Sum of discounted cash flows
NPV Project B = 2.31
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
Discount rate 10.000%
Year 0 1 2 3
Cash flow stream -20 5 9 12
Discounting factor 1.000 1.100 1.210 1.331
Discounted cash flows project -20.000 4.545 7.438 9.016
NPV = Sum of discounted cash flows
NPV Project A = 1.00
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project A
Discount rate 15.000%
Year 0 1 2 3
Cash flow stream -20 5 9 12
Discounting factor 1.000 1.150 1.323 1.521
Discounted cash flows project -20.000 4.348 6.805 7.890
NPV = Sum of discounted cash flows
NPV Project A = -0.96
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project B
Discount rate 15.000%
Year 0 1 2 3
Cash flow stream -13 8 7 3
Discounting factor 1.000 1.150 1.323 1.521
Discounted cash flows project -13.000 6.957 5.293 1.973
NPV = Sum of discounted cash flows
NPV Project B = 1.22
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor

b

IRR is same for all WACCs

Project A
IRR is the rate at which NPV =0
IRR 12.46%
Year 0 1 2 3
Cash flow stream -20.000 5.000 9.000 12.000
Discounting factor 1.000 1.125 1.265 1.422
Discounted cash flows project -20.000 4.446 7.116 8.437
NPV = Sum of discounted cash flows
NPV Project A = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 12.46%
Project B
IRR is the rate at which NPV =0
IRR 21.49%
Year 0 1 2 3
Cash flow stream -13.000 8.000 7.000 3.000
Discounting factor 1.000 1.215 1.476 1.793
Discounted cash flows project -13.000 6.585 4.742 1.673
NPV = Sum of discounted cash flows
NPV Project B = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 21.49%

Related Solutions

NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$29 $15 $13 $3 Project B -$16 $8 $3 $6 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0   1...
NPV Your division is considering two projects with the following cash flows (in millions): 0   1 2 3 Project A -$19 $8 $15 $17 Project B -$17 $11 $8 $6 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$19 $8 $15 $17 Project B -$17 $11 $8 $6 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 a. What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$17 $8 $8 $3 Project B -$26 $13 $10 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$31 $7 $12 $22 Project B -$19 $13 $6 $5 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$27 $13 $17 $8 Project B -$25 $14 $11 $2 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$31 $7 $12 $22 Project B -$19 $13 $6 $5 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A - $35 $4 $14 $20 Project B - $15 $8 $5 $4 B. What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Project A   % Project B   % What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places. Do not round...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1...
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$17 $8 $8 $3 Project B -$26 $13 $10 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Do not round your intermediate calculations. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative value should be indicated by a minus sign. Project A    $   million...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT