In: Finance
NPV
Your division is considering two projects with the following cash flows (in millions):
| 0 | 1 | 2 | 3 |
| Project A | -$20 | $5 | $9 | $12 |
| Project B | -$13 | $8 | $7 | $3 |
What are the projects' NPVs assuming the WACC is 5%? Round your
answer to two decimal places. Enter your answer in millions. For
example, an answer of $10,550,000 should be entered as 10.55.
Project A $ million
Project B $ million
What are the projects' NPVs assuming the WACC is 10%? Round your
answer to two decimal places. Enter your answer in millions. For
example, an answer of $10,550,000 should be entered as 10.55.
Project A $ million
Project B $ million
What are the projects' NPVs assuming the WACC is 15%? Round your
answer to two decimal places. Enter your answer in millions. For
example, an answer of $10,550,000 should be entered as 10.55.
Project A $ million
Project B $ million
What are the projects' IRRs assuming the WACC is 5%? Round your
answer to two decimal places.
Project A %
Project B %
What are the projects' IRRs assuming the WACC is 10%? Round your
answer to two decimal places.
Project A %
Project B %
What are the projects' IRRs assuming the WACC is 15%? Round your
answer to two decimal places.
Project A %
Project B %
a
| Project A | ||||
| Discount rate | 5.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -20 | 5 | 9 | 12 |
| Discounting factor | 1.000 | 1.050 | 1.103 | 1.158 |
| Discounted cash flows project | -20.000 | 4.762 | 8.163 | 10.366 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | 3.29 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project B | ||||
| Discount rate | 5.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -13 | 8 | 7 | 3 |
| Discounting factor | 1.000 | 1.050 | 1.103 | 1.158 |
| Discounted cash flows project | -13.000 | 7.619 | 6.349 | 2.592 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 3.56 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project B | ||||
| Discount rate | 10.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -13 | 8 | 7 | 3 |
| Discounting factor | 1.000 | 1.100 | 1.210 | 1.331 |
| Discounted cash flows project | -13.000 | 7.273 | 5.785 | 2.254 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 2.31 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project A | ||||
| Discount rate | 10.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -20 | 5 | 9 | 12 |
| Discounting factor | 1.000 | 1.100 | 1.210 | 1.331 |
| Discounted cash flows project | -20.000 | 4.545 | 7.438 | 9.016 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | 1.00 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project A | ||||
| Discount rate | 15.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -20 | 5 | 9 | 12 |
| Discounting factor | 1.000 | 1.150 | 1.323 | 1.521 |
| Discounted cash flows project | -20.000 | 4.348 | 6.805 | 7.890 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | -0.96 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| Project B | ||||
| Discount rate | 15.000% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -13 | 8 | 7 | 3 |
| Discounting factor | 1.000 | 1.150 | 1.323 | 1.521 |
| Discounted cash flows project | -13.000 | 6.957 | 5.293 | 1.973 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 1.22 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
b
IRR is same for all WACCs
| Project A | ||||
| IRR is the rate at which NPV =0 | ||||
| IRR | 12.46% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -20.000 | 5.000 | 9.000 | 12.000 |
| Discounting factor | 1.000 | 1.125 | 1.265 | 1.422 |
| Discounted cash flows project | -20.000 | 4.446 | 7.116 | 8.437 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project A = | 0.000 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| IRR= | 12.46% | |||
| Project B | ||||
| IRR is the rate at which NPV =0 | ||||
| IRR | 21.49% | |||
| Year | 0 | 1 | 2 | 3 |
| Cash flow stream | -13.000 | 8.000 | 7.000 | 3.000 |
| Discounting factor | 1.000 | 1.215 | 1.476 | 1.793 |
| Discounted cash flows project | -13.000 | 6.585 | 4.742 | 1.673 |
| NPV = Sum of discounted cash flows | ||||
| NPV Project B = | 0.000 | |||
| Where | ||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||
| IRR= | 21.49% | |||