In: Accounting
The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:
Standard Hours | Standard Rate | Standard Cost | |
Motor tune-up | 2.50 | $35.00 | $87.50 |
The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 60 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups:
Labor rate variance | $ | 50 | F |
Labor spending variance | $ | 55 | U |
Required:
1. Determine the number of actual labor-hours spent on tune-ups during the week.
2. Determine the actual hourly rate of pay for tune-ups last week. (Round your answer to 2 decimal places.)
|
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy:
Direct materials: 7 microns per toy at $0.31 per micron
Direct labor: 1.2 hours per toy at $6.70 per hour
During July, the company produced 5,000 Maze toys. The toy's production data for the month are as follows:
Direct materials: 78,000 microns were purchased at a cost of $0.28 per micron. 34,250 of these microns were still in inventory at the end of the month.
Direct labor: 6,400 direct labor-hours were worked at a cost of $46,080.
Required:
1. Compute the following variances for July: (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Do not round intermediate calculations. Round final answer to the nearest whole dollar amount.)
a. The materials price and quantity variances.
b. The labor rate and efficiency variances.
|