In: Accounting
Bentley Enterprises
uses process costing to control costs in the manufacture of Dust
Sensors for the mining industry. The following information pertains
to operations for November. (CMA Exam adapted)
Units | |||
Work in process, November 1st | 17,500 | ||
Started in production during November | 115,000 | ||
Work in process, November 30th | 25,500 | ||
The beginning inventory was 70% complete as to materials and 10%
complete as to conversion costs. The ending inventory was 90%
complete as to materials and 30% complete as to conversion
costs.
Costs pertaining to November are as follows:
Beginning inventory: direct materials, $56,060; direct labor,
$21,820; manufacturing overhead, $16,740.
Costs incurred during the month: direct materials, $483,000; direct
labor, $197,880; manufacturing overhead, $406,160.
What are the total costs in the ending Work-in-Process Inventory
assuming Bentley uses weighted-average process costing?
Multiple Choice
$138,079.
$135,784.
$100,050.
$135,779.
Correct answer------------$138,079.
Working
Reconciliation of Units | ||
A | Beginning WIP | 17,500 |
B | Introduced | 115,000 |
C=A+B | TOTAL | 132,500 |
D | Transferred out | 107,000 |
E=C-D | Ending WIP | 25,500 |
.
Statement of Equivalent Units(Weighted average) | |||||||
Material | Conversion cost | ||||||
Units | Complete % | Equivalent units | Complete % | Equivalent units | |||
Transferred out | 107,000 | 100% | 107,000 | 100% | 107,000 | ||
Ending WIP | 25,500 | 90% | 22,950 | 30% | 7,650 | ||
Total | 132,500 | Total | 129,950 | Total | 114,650 |
.
Cost per Equivalent Units (Weighted average) | ||||
COST | Material | Conversion cost | TOTAL | |
Beginning WIP Inventory Cost | $ 56,060 | $ 38,560 | $ 94,620 | |
Cost incurred during period | $ 483,000 | $ 604,040 | $ 1,087,040 | |
Total Cost to be accounted for | $ 539,060 | $ 642,600 | $ 1,181,660 | |
Total Equivalent Units | 129,950 | 114,650 | ||
Cost per Equivalent Units | $ 4.15 | $ 5.60 | $ 9.75 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | Transferred | ||
Units | Cost Allocated | Units | Cost Allocated | ||
Material | $ 4.15 | 22,950 | $ 95,201.44 | 107,000 | $ 443,858.56 |
Conversion cost | $ 5.60 | 7,650 | $ 42,877.37 | 107,000 | $ 599,722.63 |
TOTAL | $ 1,181,660 | TOTAL | $ 138,079 | TOTAL | $ 1,043,581 |