Question

In: Accounting

Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours: 40,000...

Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours:

40,000 44,000 48,000 52,000
Variable manufacturing overhead $80,000 $88,000 $96,000 $104,000
Fixed manufacturing overhead 325,000 325,000 325,000 325,000

Each product requires four hours of machine time, and the company expects to produce 10,000 units for the year. Production is expected to be evenly distributed throughout the year.
a. Calculate separate predetermined variable and fixed OH rates using as the basis of application (1) units of production and (2) machine hours.
Note: Do not round your answers.

Variable OH Rate Fixed OH Rate
(1) Units of product
(2) Machine hours

b. Calculate the combined predetermined OH rate using (1) units of product and (2) machine hours.
Note: Do not round your answers.

Combined Rate
(1) Units of product
(2) Machine hours

c. Assume that all actual overhead costs are equal to expected overhead costs for the year, but that Lansing Mfg. produced 11,000 units of product. If the separate rates based on units of product calculated in (a) were used to apply overhead, what amounts of underapplied or overapplied variable and fixed overhead exist at year-end?
Note: Do not use a negative sign with your answer.

Variable OH OverappliedUnderappliedNeither over or under applied
Fixed OH OverappliedUnderappliedNeither over or under applied

Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours:

40,000 44,000 48,000 52,000
Variable manufacturing overhead $80,000 $88,000 $96,000 $104,000
Fixed manufacturing overhead 325,000 325,000 325,000 325,000

Each product requires four hours of machine time and the company expects to produce 10,000 units for the year. Assume that Lansing Mfg. has decided to use units of production to apply overhead to production. In April of the current year, the company produced 900 units and incurred $7,500 and $26,500 of variable and fixed overhead, respectively.

a. What amount of variable manufacturing overhead should be applied to production in April?
Applied VOH $Answer



b. What amount of fixed manufacturing overhead should be applied to production in April?
Applied FOH $Answer



c. Calculate the under- or overapplied variable and fixed overhead for April.
Note: Do not use negative signs with your answers.

Variable OH OverappliedUnderappliedNeither over- or underapplied
Fixed OH OverappliedUnderappliedNeither over- or underapplied

Solutions

Expert Solution

Since the company expects to produce 10,000 units for the year and each unit requires four hours of machine time, therefore total hours of machine time is equal to 10,000 units* 4 hours per unit = 40,000 machine hours.

a)

Calculation of predetermined variable and fixed overheads on basis of (1) units of production

Variable overhead rate = Total Variable Overheads / Units of production

= $80,000 / 10,000 units

= $8 per unit

Fixed overhead rate = Total Fixed Overheads / Units of production

= $325,000 / 10,000 units

= $32.5 per unit

Calculation of predetermined variable and fixed overheads on basis of (2) Machine Hours

Variable overhead rate = Total Variable Overheads / Machine Hours

= $80,000 / 40,000 units

= $2 per unit

Fixed overhead rate = Total Fixed Overheads / Machine Hours

= $325,000 / 40,000 units

= $8.125 per unit

.

Variable OH Rate Fixed OH Rate
(1) Units of product

$8 per unit

$32.5 per unit

(2) Machine hours

$2 per unit

$8.125 per unit

b)

Calculation of Predetermined Combined Overhead Rate using (1) Units of Production

Predetermined Overhead Rate = Total Combined Overheads / Units of Production

= ($80,000 + $325,000) / 10,000 units

= $405,000 / 10,000 units

= $40.5 per unit

Calculation of Predetermined Combined Overhead Rate using (2) Machine Hours

Predetermined Overhead Rate = Total Combined Overheads / Machine Hours

= ($80,000 + $325,000) / 40,000 hours

= $405,000 / 40,000 hours

= $10.125 per unit

.

Combined Rate
(1) Units of product

$40.5 per unit

(2) Machine hours

$10.125 per unit

c) Actual Overheads = Predetermined Overheads

Therefore applied Overheads as per rate calculated in (a) :

Variable Overheads = $8 per unit * 11,000 units = $88,000

Fixed Overheads = $32.5 per unit * 11,000 units = $357,500

While actual overheads were $80,000 and $325,000 respectively.(as given that actual overheads are equal to predetermined overheads)

Therefore, both variable and fixed overheads are over applied as applied overheads are more than actual overheads.

Over-applied variable overheads = $88,000 - $80,000 = $8,000

Over-applied fixed overheads = $357,500 - $325,000 = $32,500

For April:

Units Produced = 900 units

Actual Variable Overheads = $7,500

Actual Fixed Overheads = $26,500

Rate of applying overheads on basis of units of production:

Variable overhead rate = Total Variable Overheads / Units of production

= $80,000 / 10,000 units

= $8 per unit

Fixed overhead rate = Total Fixed Overheads / Units of production

= $325,000 / 10,000 units

= $32.5 per unit

a) Amount of variable manufacturing overheads to be applied

=Variable overhead rate * Actual Units Produced

= $8 per unit * 900 units

= $7,200

b) Amount of fixed manufacturing overheads to be applied

=Fixed overhead rate * Actual Units Produced

= $32.5 per unit * 900 units

= $29,250

c) Variable Overheads:

Applied = $7,200

Actual = $7,500

Since Actual is more than the applied overheads, it is the case of under applied overheads of $300 [$7,500 - $7,200]

Fixed Overheads

Applied = $29,250

Actual = $26,500

Since Actual is less than the applied overheads, it is the case of over applied overheads of $2,750 [$29,250 - $26,500]


Related Solutions

Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours: 40,000...
Lansing Mfg. prepared the following annual abbreviated flexible budget for different levels of machine hours: 40,000 44,000 48,000 52,000 Variable manufacturing overhead $80,000 $88,000 $96,000 $104,000 Fixed manufacturing overhead 325,000 325,000 325,000 325,000 Each product requires four hours of machine time and the company expects to produce 10,000 units for the year. Assume that Lansing Mfg. has decided to use units of production to apply overhead to production. In April of the current year, the company produced 900 units and...
How to prepare a flexible budget for different levels of activity
How to prepare a flexible budget for different levels of activity
Flexible Budget with Different Levels of Production Bowling Company budgeted the following amounts: Variable costs of...
Flexible Budget with Different Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 Required: Prepare a flexible budget for 2,500 units, 3,000 units, and 3,500 units. Bowling Company Flexible Budget 2,500 units 3,000 units 3,500 units Direct materials $ $ $ Direct labor Variable overhead Fixed overhead: Materials handling...
The monthly flexible overhead budget and activities of Forest Ltd. are as follows: Machine hours -...
The monthly flexible overhead budget and activities of Forest Ltd. are as follows: Machine hours - 4,000; 5,200; 6,500 and Budgeted monthly overhead cost (Rs)- 98,000; 1,12,400; 1,28,000 respectively. The budgeted fixed overhead cost per month at the level of 6,800 machine hours is: a) Rs 30,000 b) Rs 40,000 c) Rs 45,000 d) Rs 50,000
Snyder Stampings allocates overhead to products based on machine hours. It uses a flexible overhead budget...
Snyder Stampings allocates overhead to products based on machine hours. It uses a flexible overhead budget to calculate a predetermined overhead rate at the beginning of the year. This rate is used during the year to allocate overhead to the various stampings produced. The following table summarizes operations for the last year: Budgeted fixed overhead                                $ 3,800,000 Over-absorbed overhead variance                      $ 220,000 Actual machine hours                                            46,000 Variable overhead per machine hour                        $ 100 Actual overhead incurred                               $ 8,750,000 Required: In...
Steering Company estimated the following annual hours and costs: Expected annual direct labor hours 40,000 Expected...
Steering Company estimated the following annual hours and costs: Expected annual direct labor hours 40,000 Expected annual direct labor cost $1,400,000 Expected machine hours 40,000 Expected material cost for the year $1,792,000 Expected manufacturing overhead $2,240,000 (a) Calculate predetermined overhead allocation rates using each of the four possible allocation bases provided. (Round direct labor cost and direct material cost answers to 2 decimal places, e.g. 15.25 and all other answers to 0 decimal places, e.g. 5,275.) Direct labor hours Direct...
Steering Company estimated the following annual hours and costs: Expected annual direct labor hours 40,000 Expected...
Steering Company estimated the following annual hours and costs: Expected annual direct labor hours 40,000 Expected annual direct labor cost $1,400,000 Expected machine hours 40,000 Expected material cost for the year $1,792,000 Expected manufacturing overhead $2,240,000 Direct labor hours Direct labor cost Machine hours Direct material cost Predetermined overhead allocation $56 $1.60 $56 $1.25 Determine the cost of the following job (number 253) using each of the four overhead allocation rates: (Round answers to 0 decimal places, e.g. 125.) Job...
Webster Manufacturing uses a flexible budget for manufacturing costs based on machine hours. Variable manufacturing costs...
Webster Manufacturing uses a flexible budget for manufacturing costs based on machine hours. Variable manufacturing costs per machine hour are as follows:          Indirect labor                                            $5.00          Indirect materials                                        2.50          Maintenance                                                 .50          Utilities                                                         .30 Fixed costs per month are:          Supervision                                             $1,200          Insurance                                                     400          Property taxes                                              600          Depreciation                                             1,800 Part A:  The Company believes it will normally operate in a range of 4,000 to 8,000 machine hours per month, selling at a price of $10 per machine hour. Instructions Prepare a flexible budget using increments of 2,000 machine hours within the activity...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,100 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,100 machine-hours Variable overhead costs: Supplies $ 15,810 Indirect labor 27,900 Fixed overhead costs: Supervision 17,000 Utilities 6,500 Depreciation 7,500 Total overhead cost $ 74,710 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,000 machine-hours rather than 3,100 machine-hours? Multiple Choice $72,650 $72,300 $73,300 $74,710
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $165,600    Power and light 5,760    Indirect materials 46,800       Total variable overhead cost $218,160 Fixed overhead cost:    Supervisory salaries $76,360    Depreciation of plant and equipment 48,000    Insurance and property taxes 30,540       Total fixed overhead cost 154,900 Total factory...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT