In: Operations Management
Imagine a market research project (say a manufacturing company intends to know customer response about a new product to be launched). Create the WBSs up to first level of breakdown. Work out sequence of activities and estimate time duration of each activity. Based upon your estimation, prepare schedule of the project by CPM Method as well as PERT method.
Write it in the details as it is the assignment .
Work breakdown structure:
CPM schedule:
Activity |
Preceding activity |
Time |
Initiation phase |
---------------- |
1 week |
Requirement gathering and analysis |
Initiation phase |
2 weeks |
Planning phase |
Requirement gathering and analysis |
1 week |
Project plan development |
Planning phase |
1 week |
Execution phase |
Project plan development |
1 week |
Brainstorming marketing |
Execution phase |
1 week |
Primary market research |
Brainstorming marketing |
4 weeks |
Report writing |
Primary market research |
1 week |
Close out phase |
Report writing |
1 week |
PERT schedule:
Activity |
Preceding activity |
Optimistic time (Days) |
Normal time (Days) |
Pessimistic time (Days) |
Initiation phase |
---------------- |
5 |
7 |
10 |
Requirement gathering and analysis |
Initiation phase |
10 |
14 |
20 |
Planning phase |
Requirement gathering and analysis |
4 |
7 |
8 |
Project plan development |
Planning phase |
5 |
7 |
9 |
Execution phase |
Project plan development |
4 |
7 |
8 |
Brainstorming marketing |
Execution phase |
5 |
7 |
8 |
Primary market research |
Brainstorming marketing |
20 |
28 |
35 |
Report writing |
Primary market research |
6 |
7 |
9 |
Close out phase |
Report writing |
3 |
7 |
8 |