In: Finance
2) Project K costs $44,657.75, its expected cash inflows
are $10,000 per year for 9 years, and its WACC is 13%. What is the
project's IRR?
3) Project K costs $55,000, its expected cash inflows are $8,000
per year for 12 years, and its WACC is 14%. What is the project's
payback?
Please show all work & formulas
2
| Project K | ||||||||||
| IRR is the rate at which NPV =0 | ||||||||||
| IRR | 0.169 | |||||||||
| Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 
| Cash flow stream | -44657.8 | 10000 | 10000 | 10000 | 10000 | 10000 | 10000 | 10000 | 10000 | 10000 | 
| Discounting factor | 1 | 1.169 | 1.366561 | 1.59751 | 1.8674888 | 2.183094 | 2.552037 | 2.983331 | 3.487514 | 4.076904 | 
| Discounted cash flows project | -44657.8 | 8554.32 | 7317.639 | 6259.743 | 5354.7846 | 4580.654 | 3918.438 | 3351.958 | 2867.372 | 2452.842 | 
| NPV = Sum of discounted cash flows | ||||||||||
| NPV Project K = | 0.000526 | |||||||||
| Where | ||||||||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||||||
| Discounted Cashflow= | Cash flow stream/discounting factor | |||||||||
| IRR= | 0.169 | =16.9% | ||||||||
| Accept project as IRR is more than discount rate | ||||||||||
3)
| Project K | ||
| Year | Cash flow stream | Cumulative cash flow | 
| 0 | -55000 | -55000 | 
| 1 | 8000 | -47000 | 
| 2 | 10000 | -37000 | 
| 3 | 10000 | -27000 | 
| 4 | 10000 | -17000 | 
| 5 | 10000 | -7000 | 
| 6 | 10000 | 3000 | 
| 7 | 10000 | 13000 | 
| 8 | 10000 | 23000 | 
| 9 | 10000 | 33000 | 
| 10 | 10000 | 43000 | 
| Payback period is the time by which undiscounted cashflow cover the intial investment outlay | ||
| this is happening between year 5 and 6 | ||
| therefore by interpolation payback period = 5 + (0-(-7000))/(3000-(-7000)) | ||
| 5.7 Years | ||