The Rover 6 is a new custom-designed sports car. An analysis of the task of building the Rover 6 reveals the following list of relevant activities, their immediate predecessors, and their duration:2 JOB LETTER DESCRIPTION IMMEDIATE PREDECESSOR(S) NORMAL TIME (DAYS) A Start - 0 B Design A 8 C Order special accessories B 0.1 D Build frame B 1 E Build doors B 1 F Attach axles, wheels, gas tank D 1 G Build body shell B 2 H Build transmission and drivetrain B 3 I Fit doors to body shell G,E 1 J Build engine B 4 K Bench-test engine J 2 L Assemble chassis F,H,K 1 M Road-test chassis L 0.5 N Pain body I 2 O Install wiring N 1 P Install interior N 1.5 Q Accept delivery of special accessories C 5 R Mount body and accessories M, O, P,Q 1 S Road test car R 0.5 T Attach exterior trim S 1 U Finish T 0 a) Draw a network diagram for the project. b) Mark the critical path and state its length. c) If the Rover 6 had to be completed 2 days earlier, would it help to: I. Buy preassembled transmissions and drivetrains? II. Install robots to halve engine-building time? III. Speed delivery of special accessories by 3days? d) How might resources be borrowed from activities on the noncritical path to speed activities on the critical path?
a.The network diagram is given below :-
b.The possible paths are :-
A – B – E – I – N- O: 0+8+1.5+1.5+3+2 = 16 days
A-B-E-I-N-P : 0+8+1.5+1.5+3+2.5 = 16.5 days
A-B-G-I-N-O : 0+8+2+1.5+3+2 = 16.5 days
A-B-G-I-N-P : 0+8+ 2+1.5+ 3+2.5 = 17 days
A-B-D-F-L-M: 0+8+ 1.5+1.5+1.5+1 = 13.5 days
A-B-H-L-M :0+8+1+1.5+1 = 11.5 days
A-B-J-K-L-M : 0+8+5+2 +1.5+1 = 17.5 days
A-B-C-Q : 0+8+0.1 + 5 = 13.1 days
The path from R to U is common to all and takes 3 days.
So, the citical path is the path with the maximum time which in this case is :-A-B-J-K-L-M-R-S-T-U
The length of the path is 17.5+3 = 20.5 Days
c. If the Rover 6 had to be completed 2 days earlier, it is would need to be completed in 18.5 days so it would help to
Install robots to halve engine-building time because in that case, it would take 2.5 days instead of the present 5 days and also reduce the order completion time by almost 2 days.
d. The resources on the non-critical path can be borrowed to reduce the time of completion of activities on the critical path and thereby reduce the overall project time.