In: Accounting
Lorenzo operates a brushless car wash. Incoming cars are put on
an automatic, continuously moving conveyor belt. A car is washed as
the conveyor belt carries it from the start station to the finish
station. After the car moves off the conveyor belt, workers dry it
and clean and vacuum the inside. Workers are managed by a single
supervisor.
Lorenzo's accountant wants to estimate total costs in October, when
11,650 cars are expected to be washed. She uses two different
methods to estimate total October costs, account analysis and
high-low, with number of cars washed as the independent variable
for both methods.
For the account analysis method, she developed cost function
parameter estimates by analyzing actual costs in February, when
9,600 cars were washed. The following are February total costs and
her fixed cost estimates:
Cost Item |
Total Cost |
Fixed Portion |
Soap, cloths, and supplies |
$4,800 |
$0 |
Water |
$5,760 |
$0 |
Car wash labor |
$28,380 |
$2,460 |
Power for conveyor |
$12,510 |
$2,910 |
Supervisor and cashier |
$3,700 |
$3,700 |
For the high-low method, she developed cost function parameter
estimates by using the actual costs in July and August, when 8,700
and 11,900 cars were washed, respectively. The following are total
costs for those two months:
Cost Item |
July |
August |
Soap, cloths, and supplies |
$4,350 |
$5,950 |
Water |
$3,480 |
$4,760 |
Car wash labor |
$23,380 |
$31,060 |
Power for conveyor |
$8,960 |
$11,520 |
Supervisor and cashier |
$3,950 |
$3,950 |
Total |
$44,120 |
$57,240 |
REQUIRED [ROUND PER-UNIT COSTS TO THE NEAREST CENT AND
TOTAL COSTS TO THE NEAREST DOLLAR.]
Part A
1. Using account analysis, what is the accountant's estimate of
total fixed costs for October?
2. Using account analysis, what is the accountant's estimate of
variable costs per unit for October?
Part B
1. Using the high-low method, what is the accountant's estimate of
total fixed costs for October?
2. Using the high-low method, what is the accountant's estimate of
total variable costs for October?
Answer to Part A:
1.
Estimated Total Fixed Cost for October = $2,460 + $2,910 +
$3,700
Estimated Total Fixed Cost for October =
$9,070
2.
Total Variable Cost for the Month of February =Total Cost –
Total Fixed Cost
Total Variable Cost for the Month of February = $4,800 + $5,760 +
$28,380 + $12,510 + $3,700 - $9,070
Total Variable Cost for the Month of February = $46,080
Variable Cost per Unit = 46,080 / 9,600
Variable Cost per Unit = $4.80
Answer to Part B:
1.
As per High-Low Method,
Variable Cost per Unit = (y2 – y1) / (x2 – x1)
Total Cost at the Highest Level of Activity (y2) = $57,240
Total Cost at the Lowest Level of Activity (y1) = $44,120
Total Units at the Highest Level of Activity = 11,900 Units
Total Units at the Lowest Level of Activity = 8,700 Units
Variable Cost per Unit = (57,240 – 44,120) / (11,900 – 8,700)
Variable Cost per Unit = 13,120 / 3,200
Variable Cost per Unit = $4.10
Total Cost = Fixed Cost + Variable Cost * X
For
August:
$57,240 = Fixed Cost + ($4.10 * 11,900)
$57,240 = Fixed Cost + $48,790
Fixed Cost = $8,450
For
July:
$44,120 = Fixed Cost + ($4.10 * 8,700)
$44,120 = Fixed Cost + $35,670
Fixed Cost = $8,450
2.
Total Variable Cost for the Month of October = $4.10 *
11,650
Total Variable Cost for the Month of October =
$47,765