Question

In: Accounting

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...


On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,100,000. During 2018, costs of $2,040,000 were incurred, with estimated costs of $4,040,000 yet to be incurred. Billings of $2,548,000 were sent, and cash collected was $2,290,000.

In 2019, costs incurred were $2,548,000 with remaining costs estimated to be $3,660,000. 2019 billings were $2,798,000, and $2,515,000 cash was collected. The project was completed in 2020 after additional costs of $3,840,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2018 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.

Year

Revenue Recognized

Gross Profit (Loss) Recognized

2018

2019

-148000

2020

Total

2018/

Record the construction costs.

Record the progress billings.

Record the cash collections.

Record the expected loss.

2019/

Record the construction costs.

Record the progress billings.

Record the cash collections.

Record the expected loss.

Balance Sheet

At December 31, 2018

Current Assets:

Current Liabilities:

Balance Sheet

At December 31, 2019

Current Assets:

Current Liabilities:

Solutions

Expert Solution

Percentage completion method 2018 2019 2020
Cost incurred in till previous year 0 2040000 4588000
ADD Cost incurred during the year 2040000 2548000 3840000
Total cost incurred till date 2040000 4588000 8428000
ADD Estimated cost to be incurred 4040000 3660000 0
Total estimated cost to be incurred 6080000 8248000 8428000
Percentage of completion (A) 34% 55.63% 100%
(cost incurred till date /total estimated cost )
Total revenue (B) 8100000 8100000 8100000
Total revenue recognized (A *B) 2717763 4505674 8100000
Less Revenue recognized in previous year 0 2717763 4505674
revenue recognized in current year 2717763 1787911 3594326
2018 2019 2020
Revenue 2717763 1787911 3594326
Less Cost incurred 2040000 2548000 3840000
Gross profit 677763 -760089 -245674
2018
1 Construction in progress 2040000
               Accounts payable 2040000
2 Contracts receivable 2548000
               Progress billings 2548000
3 Construction in progress 677763
Construction expense 2040000
               Construction revenue 2717763
4 Cash 2290000
          Contract receivable 2290000
2019
1 Construction in progress 2548000
               Accounts payable 2548000
2 Contracts receivable 2798000
               Progress billings 2798000
3 Construction expense 2548000
               Construction in progress 760089
               Construction revenue 1787911
4 Cash 2515000
          Contract receivable 2515000
Partial balance sheet
Asset 2018 2019
Contract receivable 258000 541000
Cash 2290000 4805000
Net contruction in progress 2717763 4505674
Liabilities
Accounts payable 2040000 4588000

Related Solutions

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,075,000. During 2018, costs of $2,030,000 were incurred, with estimated costs of $4,030,000 yet to be incurred. Billings of $2,536,000 were sent, and cash collected was $2,280,000. In 2019, costs incurred were $2,536,000 with remaining costs estimated to be $3,645,000. 2019 billings were $2,786,000, and $2,505,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,425,000. During 2018, costs of $2,170,000 were incurred, with estimated costs of $4,170,000 yet to be incurred. Billings of $2,704,000 were sent, and cash collected was $2,420,000. In 2019, costs incurred were $2,704,000 with remaining costs estimated to be $3,855,000. 2019 billings were $2,954,000, and $2,645,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,100,000. During 2018, costs of $2,040,000 were incurred, with estimated costs of $4,040,000 yet to be incurred. Billings of $2,548,000 were sent, and cash collected was $2,290,000. In 2019, costs incurred were $2,548,000 with remaining costs estimated to be $3,660,000. 2019 billings were $2,798,000, and $2,515,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,100,000. During 2018, costs of $2,040,000 were incurred, with estimated costs of $4,040,000 yet to be incurred. Billings of $2,548,000 were sent, and cash collected was $2,290,000. In 2019, costs incurred were $2,548,000 with remaining costs estimated to be $3,660,000. 2019 billings were $2,798,000, and $2,515,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2018, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2019, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2019 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2020 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT