Question

In: Finance

Hickock Mining is evaluating when to open a gold mine. The mine has 60,000 ounces of gold left...

Hickock Mining is evaluating when to open a gold mine. The mine has 60,000 ounces of gold left that can be mined, and mining operations will produce 7,500ounces peryear. The required return on the gold mine is 12%, and it will cost $14million to open the mine. When the mine is opened, the company will sign a contract that willguarantee the price of gold for the remaining life of the mine. If the mine is opened today, each ounce of gold will generate an aftertax cash flow of $450 per ounce.I the company waits one year, there is a 60% probability that the contract price will generate an aftertax cash flow of $500 per ounce and a 40% probability that theaftertax cash flow will be $410 per ounce. What is the NPV in one year to wait, NPV today for waiting, What is the value of the option to wait.

Solutions

Expert Solution


Hickock Mining is evaluating when to open a gold mine. The mine has 60,000 ounces of gold left that can be mined, and mining operations will produce7,500ounces per year. The required return on the gold mine is 12%, and it will cost $14million to open the mine. When the mine is opened, the companywill sign a contract that will guarantee the price of gold for the remaining life of the mine. If the mine is opened today, each ounce of gold willgenerate an aftertax cash flow of $450 per ounce. I the company waits one year, there is a 60% probability that the contract price will generate anaftertax cash flow of $500 per ounce and a 40% probability that the aftertax cash flow will be $410 per ounce. What is the NPV in one year to wait, NPVtoday for waiting, What is the value of the option to wait.


BY USING EXCEL

return on the gold mine is 12%

PMT=0

NPER=1

60% probability
FV= 7,500 X$500 =3,750,00

VALUE OUTCOME--------3,348,214
===================

return on the gold mine is 12%

PMT=0

NPER=1

40% probability
FV= 7,500 X$500 =3,0750,000

VALUE OUTCOME--------2,745,535

What is the value of the option to wait.

ANSWER 2,745,535


Related Solutions

Hickock Mining is evaluating when to open a gold mine. The mine has 60,300 ounces of...
Hickock Mining is evaluating when to open a gold mine. The mine has 60,300 ounces of gold left that can be mined, and mining operations will produce 6,700 ounces per year. The required return on the gold mine is 11 percent, and it will cost $34.7 million to open the mine. When the mine is opened, the company will sign a contract that will guarantee the price of gold for the remaining life of the mine. If the mine is...
Hickock Mining is evaluating when to open a gold mine. The mine has 45,900 ounces of...
Hickock Mining is evaluating when to open a gold mine. The mine has 45,900 ounces of gold left that can be mined, and mining operations will produce 5,100 ounces per year. The required return on the gold mine is 11 percent, and it will cost $33.1 million to open the mine. When the mine is opened, the company will sign a contract that will guarantee the price of gold for the remaining life of the mine. If the mine is...
4. Hickock Mining is evaluating when to open a gold mine. The mine has 33,600 ounces...
4. Hickock Mining is evaluating when to open a gold mine. The mine has 33,600 ounces of gold left that can be mined and mining operations will produce 4,200 ounces per year. The required return on the gold mine is 12% and it will cost $17.4 million to open the mine. When the mine is opened, the company will sign a contract that will guarantee the price of gold for the remaining life of the mine. If the mine is...
2. A mining company is evaluating when to open a gold mine. The mine has 80,000...
2. A mining company is evaluating when to open a gold mine. The mine has 80,000 ounces of gold left that can be mined and mining operations will produce 10,000 ounces per year. When the mine is opened, the company will sign a contract that will guarantee the price of gold for the remaining life of the mine. If the mine is opened today, each ounce of gold will generate an after-tax cash flow (= net or total cash flow)...
(5) A mining company is evaluating when to open a gold mine. The mine has 48,000...
(5) A mining company is evaluating when to open a gold mine. The mine has 48,000 ounces of gold left and mining operations can generate 6000 ounces/year. The required rate of return is 12% It will cost $34 million to open the mine. When the company opens the mine, it will sign a contract guaranteeing the price of gold for the remaining life of the mine. If the mine is opened today, each ounce of gold will generate an after...
Newmont Goldcorp is evaluating when to open a gold mine. The remaining life of the mine...
Newmont Goldcorp is evaluating when to open a gold mine. The remaining life of the mine is 8 years and the mining operations will produce 5800 ounces per year. The required return on the gold mine is 12 percent, and it will cost $33.8 million to open the mine. When the mine is opened, the company will sign a contract that will guarantee the price of gold for the remaining life of the mine. IF the mine is opened today,...
Flag Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in...
Flag Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South Dakota. Dan Dority, the company's geologist, has just finished his analysis of the mine site. He has estimated that the mine would be productive for eight years, after which the gold would be completely mined. Dan has taken an estimate of the gold deposits to Alma Garrett, the company's financial officer. Alma has been asked by Seth to perform an analysis of the...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South Dakota. Dan Dority, the company's geologist, has just finished his analysis of the mine site. He has estimated that the mine would be productive for eight years, after which the gold would be completely mined. Dan has taken an estimate of the gold deposits to Alma Garrett, the company's financial officer. Alma has been asked by Seth to perform an analysis of the new mine...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South Dakota. Dan Dority, the company’s geologist, has just finished his analysis of the mine site. He has estimated that the mine would be productive for eight years, after which the gold would be completely mined. Dan has taken an estimate of the gold deposits to Alma Garrett, the company’s financial officer. Alma has been asked by Seth to perform an analysis of the new...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South...
Seth Bullock, the owner of Bullock Gold Mining, is evaluating a new gold mine in South Dakota. Dan Dority, the company’s geologist, has just finished his analysis of the mine site. He has estimated that the mine would be productive for eight years, after which the gold would be completely mined. Dan has taken an estimate of the gold deposits to Alma Garrett, the company’s financial officer. Alma has been asked by Seth to perform an analysis of the new...