Question

In: Accounting

Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...

Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5]

The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year:

1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Units to be produced 8,000 11,000 10,000 9,000

In addition, 12,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $5,400.

Each unit requires 6 grams of raw material that costs $1.80 per gram. Management desires to end each quarter with an inventory of raw materials equal to 25% of the following quarter’s production needs. The desired ending inventory for the 4th Quarter is 5,000 grams. Management plans to pay for 60% of raw material purchases in the quarter acquired and 40% in the following quarter. Each unit requires 0.40 direct labor-hours and direct laborers are paid $14.50 per hour.

Required:

1.&2. Calculate the estimated grams of raw material that need to be purchased and the cost of raw material purchases for each quarter and for the year as a whole.

3. Calculate the expected cash disbursements for purchases of materials for each quarter and for the year as a whole.

4. Calculate the estimated direct labor cost for each quarter and for the year as a whole. Assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the estimated number of units produced.

Solutions

Expert Solution


Related Solutions

Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 5,000 8,000 7,000 6,000 In addition, 6,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $2,880. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 5,000 8,000 7,000 6,000 In addition, 6,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $2,880. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 7,000 10,000 9,000 8,000 In addition, 8,750 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $5,200. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 20,000 23,000 22,000 21,000 In addition, 40,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $7,800. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 5,000 8,000 7,000 6,000 In addition, 6,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $2,880. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 12,000 15,000 14,000 13,000 In addition, 15,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $6,200. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 25,000 28,000 27,000 26,000 In addition, 50,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $8,800. Each unit...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation...
Exercise 8-16 Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 12,000 15,000 14,000 13,000 In addition, 15,000 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $6,200. Each unit...
Exercise 8-16 (Algo) Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan...
Exercise 8-16 (Algo) Direct Materials and Direct Labor Budgets [LO8-4, LO8-5] The production department of Zan Corporation has submitted the following forecast of units to be produced by quarter for the upcoming fiscal year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 7,000 10,000 9,000 8,000 In addition, 8,750 grams of raw materials inventory is on hand at the start of the 1st Quarter and the beginning accounts payable for the 1st Quarter is $5,200. Each...
Exercise 8-10 Production and Direct Materials Budgets [LO8-3, LO8-4] Pearl Products Limited of Shenzhen, China, manufactures...
Exercise 8-10 Production and Direct Materials Budgets [LO8-3, LO8-4] Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout South East Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT