In: Finance
Question A [AR1: 5 Marks]
Consider the projects described in the table below:
End of Year |
Project A Cash Flow ($) |
Project B Cash Flow ($) |
0 |
$–90,000 |
$–90,000 |
1 |
17,000 |
0 |
2 |
17,000 |
0 |
3 |
17,000 |
0 |
4 |
17,000 |
0 |
5 |
17,000 |
0 |
6 |
17,000 |
34,000 |
7 |
17,000 |
34,000 |
8 |
17,000 |
34,000 |
9 |
17,000 |
34,000 |
10 |
17,000 |
90,000 |
Both projects have an appropriate risk adjusted discount rate of 7 percent.
Required:
a. |
Calculate the NPV and IRR for both projects |
b. |
If projects A and B are independent, which will you undertake? |
c. |
If projects A and B are mutually exclusive, which will you undertake? |
a
Project A | |||||||||||
Discount rate | 7.000% | ||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Cash flow stream | -90000 | 17000 | 17000 | 17000 | 17000 | 17000 | 17000 | 17000 | 17000 | 17000 | 17000 |
Discounting factor | 1.000 | 1.070 | 1.145 | 1.225 | 1.311 | 1.403 | 1.501 | 1.606 | 1.718 | 1.838 | 1.967 |
Discounted cash flows project | -90000.000 | 15887.850 | 14848.458 | 13877.064 | 12969.219 | 12120.765 | 11327.818 | 10586.746 | 9894.155 | 9246.874 | 8641.938 |
NPV = Sum of discounted cash flows | |||||||||||
NPV Project A = | 29400.89 | ||||||||||
Where | |||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project A | |||||||||||
IRR is the rate at which NPV =0 | |||||||||||
IRR | 13.62% | ||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Cash flow stream | -90000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 | 17000.000 |
Discounting factor | 1.000 | 1.136 | 1.291 | 1.467 | 1.667 | 1.894 | 2.152 | 2.445 | 2.778 | 3.156 | 3.586 |
Discounted cash flows project | -90000.000 | 14961.974 | 13168.275 | 11589.612 | 10200.204 | 8977.364 | 7901.123 | 6953.906 | 6120.245 | 5386.526 | 4740.769 |
NPV = Sum of discounted cash flows | |||||||||||
NPV Project A = | -0.001 | ||||||||||
Where | |||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||||||||
IRR= | 13.62% |
Project B | |||||||||||
Discount rate | 7.000% | ||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Cash flow stream | -90000 | 0 | 0 | 0 | 0 | 0 | 34000 | 34000 | 34000 | 34000 | 90000 |
Discounting factor | 1.000 | 1.070 | 1.145 | 1.225 | 1.311 | 1.403 | 1.501 | 1.606 | 1.718 | 1.838 | 1.967 |
Discounted cash flows project | -90000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 22655.636 | 21173.491 | 19788.310 | 18493.747 | 45751.436 |
NPV = Sum of discounted cash flows | |||||||||||
NPV Project B = | 37862.62 | ||||||||||
Where | |||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project B | |||||||||||
IRR is the rate at which NPV =0 | |||||||||||
IRR | 11.63% | ||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Cash flow stream | -90000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 34000.000 | 34000.000 | 34000.000 | 34000.000 | 90000.000 |
Discounting factor | 1.000 | 1.116 | 1.246 | 1.391 | 1.553 | 1.733 | 1.935 | 2.160 | 2.411 | 2.692 | 3.005 |
Discounted cash flows project | -90000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 17571.522 | 15740.957 | 14101.096 | 12632.072 | 29954.353 |
NPV = Sum of discounted cash flows | |||||||||||
NPV Project B = | 0.000 | ||||||||||
Where | |||||||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||||||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||||||||
IRR= | 11.63% |
B
Select both as NPV is positive for both
C
Select project B as it has higher NPV