CONTRACTING METHODOLOGY AND TYPE SCENARIOS SCENARIO: Karenna just returned from a Department of Defense management meeting...

CONTRACTING METHODOLOGY AND TYPE SCENARIOS

SCENARIO: Karenna just returned from a Department of Defense management meeting where the dismal state of the budget was the principle topic. She gave Bob the bad news. It is four months before the end of the year closeout and two major requirements came in from the Navy Warfare Center. The funding is dismal, resources are overloaded and Bob is the only contracting officer she can depend on to be fast and accurate when it comes to complex requirements of this nature. Bob must get these requirements on contract by October 1st. Bob must convene an acquisition team and get started right away. Bob will need to come up with an acquisition strategy to include contract methodology and contract type that will encourage efficient funds management and will motivate the contractors to watch the bottom line.

Requirement 1 -The Department of the Navy, Space and Naval Warfare Systems Center Pacific (SSC Pacific) has a requirement to provide Command, Control, Communications, Computers, and Intelligence (C4I) software support activity (SSA) for systems engineering, integration, information assurance, software maintenance, operational support, training and infrastructure support to SSC Pacific Maritime Global Command and Control System (GCCS) Family of Systems (MGF) Project and other C2 and/or C4I projects within Code 532. Period of performance includes a 3-year base period and 2-year option period. The estimated level of effort for the total requirement is 766,025 hours. The NAICS code is 541330.

Requirement 2 – The Department o the Navy, Space and Naval Warfare Systems Center Pacific (SSC Pacific) and Air Force have a requirement to contract for non personal services to provide all plant, labor, transportation, materials, tools, equipment, appliances and supervision necessary for the renovation of an existing aircraft maintenance hangar consisting of approximately 36,908 SF. The project includes but is not limited to the sustainment of interior walls, ceilings, sound attenuation, and internal and external durable surfaces to include roof and exterior metal panel wall replacement. Repair facility paint, floor coverings, millwork, caulk, protective coatings, wall systems, and hangar door structure. Install fire sprinkler systems, additional steel frame support, metal insulated panels, metal barrel roof, interior walls, HVAC systems, communications wiring, restrooms, millwork, utilities, access pavements, fire protection/detection, fire suppression, site work, anti-terrorism force protection measures, erosion control, drainage structures and landscape. Site work includes but not limited to site work including water, electrical, communications, natural gas, sanitary sewer, and storm sewer connections to existing infrastructure.

Task: You are the contracting officer for the acquisitions discussed above. Develop a viable procurement strategy to include determining the contracting method, contract type and risk.   As you determine the contract methodology and contract type keep in mind some concerns and limitations:

-The schedule is aggressive;

-Requirement 1 includes proprietary equipment;

-Limited funds;

-A need for quality because the requirements are vital to national defense.

-Security clearances are another important issue. Whoever win the contract have a Top secret facility clearance, either before or shortly after contract award;

-Past protest on both requirements.

Address the following questions in your response to requirements 1and 2 separately:

1. What contracting method will you use? Why?

2. What are the key risk areas of the efforts?

3. What contract type would motivate the contractor to achieve excellence and manage funds wisely? Why?

Solutions

Expert Solution

The requirement 1 involves working using proprietary equipments and working on more strategic services, the alliancing method should be used where team from both design team and supplier merge together and work on single mission. Here it should be used because :

a) there is high level of complexity involved.

b) the bottom line needs to be taken care of and in this structure, there can be open book accounting for both parties which should result in controlled costs.

c) both stakeholders are focussed on one single goal of the procurement

d) faster decision making

For requirement 2,Design-Bid-Build (DBB ) can be the approach used where there is less chances of risks or facing a major uncertainity because most of the tasks are regular activities. these can be governed by a service contract.

benefits are :

a) Because open bids are involved, there is clear competitive environment that is being set up here

b) costs are controlled because bid is generally given for the optimum price and quality

c) there are very less chances of corruption or rigging by officials.

Some risks that are involved are :

a) no involvement of contractor in the design phase whereas contractor could have given the valuable inputs to the design

b) it may lead to increase in schedule.


Related Solutions

Your boss has just returned from a meeting of the Birmingham Society of Human Resource Management...
Your boss has just returned from a meeting of the Birmingham Society of Human Resource Management and announced that there are several concepts drawn from economics that might have an impact on your firm. Do the following for your boss: 1. Explain the “backward bending” supply of labor curve. Explain what goes on in the curve at various points and why that occurs. 2. Your boss thinks that your firm might be pure/perfect competitor in the product market but a...
Suppose that the defense contracting business is perfectly competitive. In long -run equilibrium the price just...
Suppose that the defense contracting business is perfectly competitive. In long -run equilibrium the price just covers average production cost, and every contractor makes zero profit. Thus, if the price goes down, even a little bit, due to a decrease in government defense spending, all contractors will go out of business. Discuss this statement.
Carolyn Foster had just returned to her office from the weekly plant IR representatives’ meeting. Her...
Carolyn Foster had just returned to her office from the weekly plant IR representatives’ meeting. Her secretary had left a note to call George Lowrey, the superintendent of the forklift assembly operation. She called back and immediately recognized from the serious- ness of George’s tone that a major problem must be brewing in his area. They both agreed she would come right over. After George had welcomed her into his office, he leaned forward and, putting his chin in his...
Late in 2021, you and two other officers of Curbo Fabrications Corporation just returned from a meeting with officials of the City of Jackson.
Late in 2021, you and two other officers of Curbo Fabrications Corporation just returned from a meeting with officials of the City of Jackson. The meeting was unexpectedly favorable even though it culminated in a settlement with city authorities that required your company pay a total of $475,000 to cover the cost of violations of city construction codes. Jackson had filed suit in November 2019 against Curbo, seeking civil penalties and injunctive relief for violations of city construction codes regulating earthquake damage standards. Alleged...
Project Part 2: Gap Analysis Plan and Risk Assessment Methodology   Scenario After the productive team meeting,...
Project Part 2: Gap Analysis Plan and Risk Assessment Methodology   Scenario After the productive team meeting, Fullsoft’s chief technology officer (CTO) wants further analysis performed and a high-level plan created to mitigate future risks, threats, and vulnerabilities. As part of this request, you and your team members will create a plan for performing a gap analysis, and then research and select an appropriate risk assessment methodology to be used for future reviews of the Fullsoft IT environment. An IT gap...
what are the roles of the Department of Defense (DoD) and NORTHCOM in domestic emergency management.
what are the roles of the Department of Defense (DoD) and NORTHCOM in domestic emergency management.
Dave Johnson, Coke’s Financial Director, returned from a meeting with the following comparative financial data, which...
Dave Johnson, Coke’s Financial Director, returned from a meeting with the following comparative financial data, which was carefully verified: 2001 comparative financial information for the Italian market Coke Pepsi Regional Brands Domestic soft drink sales (000) $    22,632 $    25,744 $      158,030 COGS (on soft drinks only) 78% 70% 85% Average price per equivalent unit (in $) 6 10.5 3.5 He tells you that he is very concerned that Pepsi is achieving both higher average prices and has lower costs....
Instructions: Each of the following scenarios illustrates one of Freud’s defense mechanisms from the list below....
Instructions: Each of the following scenarios illustrates one of Freud’s defense mechanisms from the list below. Read each case, identify the defense mechanism, and explain how it is illustrated by the example. Displacement Regression projection Repression Rationalization Sublimation Reaction Formation Denial 1. After losing the soccer game by failing to stop a goal, Hester explains to her older brother, “Winning is really quite meaningless and unimportant. It has little to do with true happiness.” What defense is Hester using? 2....
Instructions: Each of the following scenarios illustrates one of Freud’s defense mechanisms from the list below....
Instructions: Each of the following scenarios illustrates one of Freud’s defense mechanisms from the list below. Read each case and identify the defense mechanism. It is possible some scenarios have more than one answer, in this case you need only indicate one choice. Displacement / Projection / Rationalization / Reaction Formation / Regression / Repression / Sublimation / Denial E. Serika notices that her 7-year-old son likes to pull wings off flies, jab pins in the cat, and trap mice...
Reorganisation - EDP Department At the monthly management meeting of Book Worm, the Managing Director has...
Reorganisation - EDP Department At the monthly management meeting of Book Worm, the Managing Director has outlined a new organisation structure. The changes are due to the planned introduction of global responsibilities for the EDP function. The major changes include: The elevation of the EDP Manager to equal status with the other function heads to be able to more effectively apply computer processing into the reporting and management activities. The Board of Directors has established the objective to increase the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT