Question

In: Finance

q1. Frye Foods is considering a project that has the following cash flow data. What is...

q1. Frye Foods is considering a project that has the following cash flow

data. What is the project's IRR? Enter your answer rounded to two

decimal places. Do not enter % in the answer box. For example, if

your answer is 0.12345 or 12.345% then enter as 12.35 in the

answer box.

Year:

0

1

2

3

4

5

Cash flows:

-$750

$325

$325

$325

$325

$325

q2. Van Auken Inc. is considering a project that has the following cash flows:

Year

Cash Flow

0

-$1,600

1

500

2

400

3

950

4

400

The company’s WACC is 10%. What is the project’s ordinary payback? Enter your answer rounded to two decimal places. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

Q3. Babcock Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Enter your answer rounded to two decimal places. Do not enter $ or comma in the answer box. For example, if your answer is $12,300.456 then enter as 12300.46 in the answer box.

WACC:

13%

Year:

0

1

2

3

Cash flows:

-$1,250

$400

$500

$600

Q4. Garvin Enterprises is considering a project that has the following cash flow and WACC data. What is the project's discounted payback? Enter your answer rounded to two decimal places. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

WACC:

12%

Year:

0

1

2

3

Cash flows:

-$1,100

$550

$550

$550

Q5. Hindelang Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box.

WACC:

11%

Year:

0

1

2

3

4

Cash flows:

-$875

$350

$375

$400

$425

Solutions

Expert Solution

1

IRR is the rate at which NPV =0
IRR 32.87%
Year 0 1 2 3 4 5
Cash flow stream -750.000 325.000 325.000 325.000 325.000 325.000
Discounting factor 1.000 1.329 1.765 2.346 3.117 4.141
Discounted cash flows project -750.000 244.601 184.092 138.551 104.276 78.480
NPV = Sum of discounted cash flows
NPV 0 = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 32.87%

2

Year Cash flow stream Cumulative cash flow
0 -1600 -1600
1 500 -1100
2 400 -700
3 950 250
4 400 650
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-700))/(250-(-700))
2.74 Years

Please ask remaining parts separately, questions are unrelated. I have done one bonus


Related Solutions

Q1. Hindelang Inc. is considering a project that has the following cash flow and WACC data....
Q1. Hindelang Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR? Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your answer is 0.12345 or 12.345% then enter as 12.35 in the answer box. WACC: 11% Year: 0 1 2 3 4 Cash flows: -$875 $350 $375 $400 $425 Q2. Anderson Associates is considering two mutually exclusive projects that have...
You are considering a project that has the following cash flow and WACC data. What is...
You are considering a project that has the following cash flow and WACC data. What is the project’s NPV? WACC: 9.00% Year: 0 1 2 3 4 5 Cash flows: –$1,000 $300 $300 $300 $300 $300 Select one: a. 150.62 b. 176.4 c. 166.90 d. 143.90
Redesign Inc. is considering a project that has the following cash flow data. (a) What is...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is the project's payback period? (b) What is the project's discounted payback period? Assume the cost of capital is 12%. Year 0 1 2 3 Cash flows -$500 $200 $200 $200
Simms Corp. is considering a project that has the following cash flow data. What is the...
Simms Corp. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 Cash flows -$1,025 $425 $425 $425
Susmel Inc. is considering a project that has the following cash flow data. What is the...
Susmel Inc. is considering a project that has the following cash flow data. What is the project's payback? No original investment given Year 0 1 2 3 Cash flows -$500 $150 $200 $300 Group of answer choices 1.90 years 2.63 years 2.50 years 1.93 years
Samsung. is considering a project that has the following cash flow data. What is the project's...
Samsung. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 Cash flows -$1,025 $425 $425 $425
Siblene Penn is considering a project that has the following cash flow data. What is the...
Siblene Penn is considering a project that has the following cash flow data. What is the discounted payback using a 11.2% cost of capital? Year 0 1 2 3 4 5 Cash flows -$6,750 $2,000 $2,025 $2,050 $2,075 $2,100
Warr Company is considering a project that has the following cash flow data. What is the...
Warr Company is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 4 Cash flows -$1565 $400 $400 $400 $400 a. 0.85% b. 0.76% c. 0.89% d. 0.91% e. 0.78%
Warr Company is considering a project that has the following cash flow data. What is the...
Warr Company is considering a project that has the following cash flow data. What is the project's IRR? Year 0 1 2 3 4 Cash flows -$1,415 $400 $400 $400 $400
Stern Associates is considering a project that has the following cash flow data. What is the...
Stern Associates is considering a project that has the following cash flow data. What is the project's payback? Show Work! Year 0 1 2 3 4 5 Cash flows -$1,000 $400 $410 $420 $430 $440
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT