In: Operations Management
A Project plan has been developed by the project team. The scheduled data are given in the following table
Activity |
predecessor |
Normal time |
Crash Time |
Normal cost |
Crash COST |
COST SLOPE |
A |
- |
12 |
7 |
3000 |
5000 |
400 |
B |
A |
8 |
5 |
2000 |
3500 |
500 |
C |
A |
4 |
3 |
4000 |
7000 |
3000 |
D |
B,C |
12 |
9 |
50000 |
71000 |
7000 |
E |
B,C |
4 |
1 |
500 |
1100 |
200 |
F |
E |
4 |
1 |
500 |
1100 |
200 |
G |
D,F |
4 |
3 |
15000 |
22000 |
7000 |
Requirements:
Note that the total cost has increased. So, the optimal cost-time trad-off is at Step-3 i.e. 27 weeks duration with total cost = $106,200
-----------------------
Repeat step-2 but this time, just reduce the duration of 'B' by one week only.
So,
the minimum cost of achieving 30-weeks duration = $107,500