In: Operations Management
Given the operation times provided:
JOB TIMES (minutes) | ||||||
A | B | C | D | E | F | |
Center 1 | 20 | 16 | 43 | 60 | 35 | 42 |
Center 2 | 27 | 30 | 51 | 12 | 28 | 24 |
a. Develop a job sequence that minimizes idle time at the
two work centers.
The sequence is
(Click to
select) A-B-C-D-E-F B-A-C-E-F-D C-A-B-D-E-F F-E-D-A-B-C E-F-D-B-C-A D-C-B-A-E-F .
b. Determine idle time of center 2, assuming no
other activities are involved.
Idle time
minutes
We will apply Johnson’s rule to solve the problem
Johnson’s Rule is:
The original table :
Job |
Centre 1 |
Centre 2 |
A |
20 |
27 |
B |
16 |
30 |
C |
43 |
51 |
D |
60 |
12 |
E |
35 |
28 |
F |
42 |
24 |
Accordingly , order of jobs using Johnson’s rule :
B --- A --- C ---- E --- F ---- D
Time taken to finish all the jobs :
Centre 1: B ( 16) A ( 36) C (79) E (114) F (156) D ( 216)
Centre 2 : B (46) A ( 73) C ( 130) E (158) F ( 182) D (228)
It will take 228 minutes to complete all the tasks.
Data in parenthesis () are the corresponding completion time of the activity.
Total job time of all activities at centre 2 = 172 minutes
But, completion time at centre 2 = 228 minutes
Therefore, idle time at centre 2 = 228 – 172 minutes = 56 minutes