Question

In: Operations Management

Given the operation times provided: JOB TIMES (minutes) A B C D E F Center 1...

Given the operation times provided:

JOB TIMES (minutes)
A B C D E F
Center 1 20 16 43 60 35 42
Center 2 27 30 51 12 28 24


a.
Develop a job sequence that minimizes idle time at the two work centers.

The sequence is             (Click to select)  A-B-C-D-E-F  B-A-C-E-F-D  C-A-B-D-E-F  F-E-D-A-B-C  E-F-D-B-C-A  D-C-B-A-E-F  .

b. Determine idle time of center 2, assuming no other activities are involved.

Idle time             minutes

Solutions

Expert Solution

We will apply Johnson’s rule to solve the problem

Johnson’s Rule is:

  1. From the list of unscheduled jobs, select the one with the shortest processing time in either work center.
  2. If the shortest time is at the first work center, do the job first in the schedule otherwise do the job last in the schedule.
  3. Remove the job assigned in Step 2 from the list of unscheduled jobs.
  4. Repeat steps 1,2 and 3 filling in the schedule from the front and the back until all jobs have been scheduled.

The original table :

Job

Centre 1

Centre 2

A

20

27

B

16

30

C

43

51

D

60

12

E

35

28

F

42

24

Accordingly , order of jobs using Johnson’s rule :

B --- A --- C ----   E --- F ---- D

Time taken to finish all the jobs :

Centre 1: B ( 16) A ( 36) C (79) E (114) F (156) D ( 216)

Centre 2 :             B (46) A ( 73) C ( 130) E (158) F ( 182) D (228)

It will take 228 minutes to complete all the tasks.

Data in parenthesis () are the corresponding completion time of the activity.

Total job time of all activities at centre 2 = 172 minutes

But, completion time at centre 2 = 228 minutes

Therefore, idle time at centre 2 = 228 – 172 minutes = 56 minutes


Related Solutions

1. Processes A, B, C, D, E, and F require service times of 3, 5, 2,...
1. Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their arrival times are 0, 1, 3, 9, 10, and 12. What is the average turnaround time, waiting time, response time, and throughput when using SRJF, RR (q=2), and MLF (q=22i+1). Show your work.
1. Processes A, B, C, D, E, and F require service times of 3, 5, 2,...
1. Processes A, B, C, D, E, and F require service times of 3, 5, 2, 5, 3, and 5. Their arrival times are 0, 1, 3, 9, 10, and 12. What is the average turnaround time, waiting time, response time, and throughput when using SRJF, RR (q=2), and MLF (q=22i+1). Show your work.
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what...
Consider the cross: A/a; b/b; C/c; D/d; E/e x A/a; B/b; c/c; D/d; e/e a) what proportion of the progeny will phenotypically resemble the first parent? b) what proportion of the progeny will genotypically resemble neither parent?
#1 We are given the grammar rules A ➝ F B E B ➝ A C...
#1 We are given the grammar rules A ➝ F B E B ➝ A C These rules are only some of the rules of a larger grammar G, but we are not given the remaining rules of G. We are told that A is the start symbol of G and that the following holds: {ε, c, d} ⊆ FIRST(C) {ε, e} ⊆ FIRST(E) {ε, f, g} ⊆ FIRST(F) Recall that end of file is denoted EOF. The symbol ⊆...
Consider the cities B,C,D,E,F,G The costs of the possible roads between cities are given below: c(B,F)...
Consider the cities B,C,D,E,F,G The costs of the possible roads between cities are given below: c(B,F) = 11 c(B,G) = 10 c(C,G) = 8 c(D,E) = 12 c(D,F) = 13 c(E,F) = 9 c(E,G ) = 7 What is the minimum cost to build a road system that connects all the cities?
Given the following knowledge base: a <- b^c. b <- d^e. b <- g^e. c <-...
Given the following knowledge base: a <- b^c. b <- d^e. b <- g^e. c <- e. d. e. ƒ <- a^g. Which of the following would be the trace of resolved atoms assuming a bottoms-up proof procedure? Select one: a. {a,b,c,e,g} b. {a,b,c,e,d} c. {g,e,b,e,c,a} d. None of these options Constraint Satisfaction Problem (CSP) is consists of a set of _________________. Select one: a. Variables, heuristics, and solutions b. Variables, domains, and backtracking c. Variables, domains, and constraints d....
Given this set of daily service operations, and assuming a processing order of A-B-C-D-E: Service Operation...
Given this set of daily service operations, and assuming a processing order of A-B-C-D-E: Service Operation Number of Daily Reps A 36 B 20 C 36 D 32 E 8 b. Determine the number of repetitions for each service if four cycles are used. Cycle 1 2 3 4 A B C D E c. Determine the number of repetitions for each service if two cycles are used. Cycle 1 2 A B C D E
If there are 7 total notes C, D, E, F, G, A, and B and if...
If there are 7 total notes C, D, E, F, G, A, and B and if a five-note melody is selected at random (so that all melodies counted in part (a) are equally likely to be chosen), what is the probability that the melody will include exactly two “A” notes, but no other repeated notes? (A few allowable examples: AACEG, ACAEG, DFACA, EAABC, etc.)
Solve the c, d, e, f from the given equations. e+2f=-1 2d+e=-0.2 2c+d+3e+4f=-0.5 -e-2f=1
Solve the c, d, e, f from the given equations. e+2f=-1 2d+e=-0.2 2c+d+3e+4f=-0.5 -e-2f=1
Seven people (A,B,C,D,E, F, and G) are seated in a row. Suppose A,B, and C are...
Seven people (A,B,C,D,E, F, and G) are seated in a row. Suppose A,B, and C are freshmen, D and E are sophomores and F and G are juniors. How many arrangements are possible if: (a) D and F must sit together? (b) A and C must not sit together? (c) All freshmen must sit together? (d) All freshmen must sit together, all sophomores must sit together, and all juniors must sit together? (e) Exactly two people sit between A and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT