Question

In: Accounting

Dream Team Productions is in the final design phases of the new film, Killer Worms, to...

Dream Team Productions is in the final design phases of the new film, Killer Worms, to be released next summer. Market Wise, the firm hired to coordinate the release of the Killer Wormstoys, identified the following activities to be completed before the release of the film.

Activity           Immediate        Optimistic       Most likely      Pessimistic      Normal Crash Crash   

                        Predecessor     Time (weeks)  Time(weeks)   Time(weeks)   Cost       Cost   time

A                     ----                   1                      2                                  4          1000       1900   1

B                     ----                   3                      3.5                               4          1000       1800   2

C                     A,B                 10                    12                                13        1500        2700  8

D                     C                     4                      5                                  7          2000        3200  4

E                      C                     2                      4                                  5          5000        8000  3

F                      E                      6                      7                                  8          3000        4100  6

G                     C                     2                      4                                  5.5       8000        5000  2

H                     D,F,G              5                      7.7                               9          5000        6400  7

I                       D,F                  9.9                   10                                12        10000        ----- -

J                      H                     2                      4                                  5          4000          ----- -

K                     I,J                    2                      4                                  6          5000          ----- -

- - 1). Determine a crashing schedule.

Solutions

Expert Solution

Explanation :

Crashing Schedule means the Schedule which contains the details of how much time an activity can be crashed and what is the incremental cost associated with it. In the above case, there are activities from A- K. Of which, I,J,K Activities can not be crashed because the crash time is not given, which means that these activities are to be completed within the normal time. Since, there is no crash time and crash cost, these are not shown in Crashing Schedule. Even if those are shown, it does not have any impact. Whereas, for the other activities, the normal time, crash time and normal cost, crash cost are different.

Normal time means the average time with in which the activity is required to be completed.

Crash Time means the least time (i.e., minimum time) required to complete the Activity.

Since, the Activity is to be completed in less time, it needs to be employ more resources, workmen to complete, which requires an extra cost. This cost is called as Crash Cost. The Cost which is incurred to complete the Activity in Crash Time.

For E.g : For the Activity-A, the Average time required is 2.17 weeks. and if the Activity-A takes 2.17 weeks it will incur $ 1,000. It is said that the Activity-A can also be completed in 1 week. If so, then it will incur $ 1,900. Which means to decrease the Activity time by 1.17 weeks, it will incur an additional amount of $ 900. In other words, it costs $ 771.43 for 1 week of saving in time.

The Crashing Schedule specifies the same for all the Activities.


Related Solutions

3D Productions is considering a new packaging design for the virtual reality goggles the company produces....
3D Productions is considering a new packaging design for the virtual reality goggles the company produces. Management estimates that the new design will result in the following probabilities for possible effects on the firm's current estimate of annual sales of $8 million: Probability .05 .20 .40 .20 .15 Change in Sales ( 30,000) 40,000 100,000 150,000 250,000 The machinery required to incorporate the new design in the packaging is priced at $600,000. Since the new machine is technically superior to...
The lead architect on the design team of a new skyscraper decides that the outer surface...
The lead architect on the design team of a new skyscraper decides that the outer surface of the building’s windows need to be coated with a reflective layer in order to lower airconditioning costs. MgF2 is chosen for the reflective layer, which has a refractive index n=1.38. Assume that the refractive index of the window glass is 1.5 and that the reflective coating should work optimally at the peak of the sunlight spectrum, 500 nm. Part A) What is the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT