Question

In: Accounting

Problem 20-3A Case Inc. is a construction company specializing in custom patios. The patios are constructed...

Problem 20-3A

Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data.

Raw Materials Inventory $4,998 Manufacturing Overhead Applied $38,842
Work in Process Inventory $6,593 Manufacturing Overhead Incurred $37,664


Subsidiary data for Work in Process Inventory on June 1 are as follows.

Job Cost Sheets
Customer Job
Cost Element
Rodgers
Stevens
Linton
Direct materials $714 $952 $1,071
Direct labor 381 643 690
Manufacturing overhead 476 803 863
$1,571 $2,398 $2,624


During June, raw materials purchased on account were $5,831, and all wages were paid. Additional overhead costs consisted of depreciation on equipment $1,071 and miscellaneous costs of $476 incurred on account.

A summary of materials requisition slips and time tickets for June shows the following.

Customer Job
Materials Requisition Slips
Time Tickets
Rodgers $952 $1,012
Koss 2,380 952
Stevens 595 428
Linton 1,547 1,428
Rodgers 357 464
5,831 4,284
General use 1,785 1,428
$7,616 $5,712


Overhead was charged to jobs at the same rate of $1.25 per dollar of direct labor cost. The patios for customers Rodgers, Stevens, and Linton were completed during June and sold for a total of $22,491. Each customer paid in full.

[Partially correct answer.] Your answer is partially correct. Try again.

Journalize the June transactions: (1) for purchase of raw materials, factory labor costs incurred, and manufacturing overhead costs incurred; (2) assignment of direct materials, labor, and overhead to production; and (3) completion of jobs and sale of goods. (Credit account titles are automatically indented when amount is entered. Do not indent manually. Round answers to 0 decimal places, e.g. 2,500.)

No.
Account Titles and Explanation
Debit
Credit
(1)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record purchase of raw materials)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record factory labor costs paid)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record manufacturing overhead costs incurred)
(2)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record assignment of direct materials)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record assignment of factory labor)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record assignment of manufacturing overhead)
(3)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record completion of jobs)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record sale of goods)
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with incorrect answer]
(To record the cost of goods sold)

LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT

[Partially correct answer.] Your answer is partially correct. Try again.

Post the entries to Work in Process Inventory. (Round answers to 0 decimal places, e.g. 2,500.)

Work in Process Inventory
6/1
[Entry field with correct answer]

Completed Work
Overhead Applied
Balance
Direct Materials
Direct Labor
[Entry field with incorrect answer]
June
[Entry field with correct answer]

Overhead Applied
Completed Work
Balance
Direct Materials
Direct Labor
[Entry field with incorrect answer]
[Entry field with correct answer]

Completed Work
Balance
Direct Materials
Direct Labor
Overhead Applied
[Entry field with incorrect answer]

[Entry field with correct answer]

Direct Labor
Balance
Direct Materials
Completed Work
Overhead Applied
[Entry field with incorrect answer]


[Entry field with correct answer]

Completed Work
Balance
Direct Materials
Overhead Applied
Direct Labor
[Entry field with incorrect answer]

6/30
[Entry field with correct answer]

Balance
Direct Materials
Overhead Applied
Completed Work
Direct Labor
[Entry field with incorrect answer]

LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT

[Incorrect answer.] Your answer is incorrect. Try again.

Reconcile the balance in Work in Process Inventory with the costs of unfinished jobs. (Round answers to 0 decimal places, e.g. 2,500.)

Costs of unfinished Job:
[Entry field with incorrect answer]

Rodgers
Koss
Linton
Stevens
Direct Materials $
[Entry field with incorrect answer]
+ Direct Labor $
[Entry field with incorrect answer]
+ Manufacturing Overhead $
[Entry field with incorrect answer]
= $
[Entry field with incorrect answer]

LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT
LINK TO TEXT

[Partially correct answer.] Your answer is partially correct. Try again.

Prepare a cost of goods manufactured schedule for June. (Round answers to 0 decimal places, e.g. 2,500.)

CASE INC.
Cost of Goods Manufactured Schedule
[Entry field with correct answer]

For the Year Ended June 30, 2017
June 30, 2017
For the Month Ended June 30, 2017
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Raw Materials, June 1
Raw Materials, June 30
Finished Goods, June 1
Finished Goods, June 30
$
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Finished Goods, June 1
Finished Goods, June 30
Raw Materials, June 1
Raw Materials, June 30
$
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Raw Materials, June 1
Raw Materials, June 30
Finished Goods, June 1
Finished Goods, June 30
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Finished Goods, June 1
Finished Goods, June 30
Raw Materials, June 1
Raw Materials, June 30
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Raw Materials, June 1
Raw Materials, June 30
Finished Goods, June 1
Finished Goods, June 30
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Finished Goods, June 1
Finished Goods, June 30
Raw Materials, June 1
Raw Materials, June 30
[Entry field with incorrect answer]
[Entry field with correct answer]

Add
Less
:
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Raw Materials, June 30
Raw Materials, June 1
Finished Goods, June 1
Finished Goods, June 30
[Entry field with incorrect answer]
[Entry field with correct answer]

Cost of Goods Manufactured
Direct Labor
Direct Materials Used
Manufacturing Overhead Applied
Total Cost of Work in Process
Total Manufacturing Costs
Work in Process, June 1
Work in Process, June 30
Finished Goods, June 30
Finished Goods, June 1
Raw Materials, June 1
Raw Materials, June 30
$
[Entry field with incorrect answer]

Solutions

Expert Solution


Related Solutions

Problem 20-3A Case Inc. is a construction company specializing in custom patios. The patios are constructed...
Problem 20-3A Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,368 Manufacturing Overhead Applied $33,946 Work in Process Inventory $5,762 Manufacturing Overhead Incurred $32,916 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton...
Problem 16-3A Case Inc. is a construction company specializing in custom patios. The patios are constructed...
Problem 16-3A Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $ 4,662 Manufacturing Overhead Applied $ 36,230 Work in Process Inventory $ 6,149 Manufacturing Overhead Incurred $ 35,132 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,800 Manufacturing Overhead Applied $35,800 Work in Process Inventory $4,800 Manufacturing Overhead Incurred $29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,200 Manufacturing Overhead Applied $32,640 Work in Process Inventory $5,540 Manufacturing Overhead Incurred $31,650 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $ 4,536 Manufacturing Overhead Applied $ 35,251 Work in Process Inventory $ 5,983 Manufacturing Overhead Incurred $ 34,182 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,900 Manufacturing Overhead Applied $31,800 Work in Process Inventory $5,475 Manufacturing Overhead Incurred $34,600 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,100 Manufacturing Overhead Applied $33,800 Work in Process Inventory $5,675 Manufacturing Overhead Incurred $28,600 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2017, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $ 4,326 Manufacturing Overhead Applied $ 33,619 Work in Process Inventory $ 5,706 Manufacturing Overhead Incurred $ 32,600 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $4,600 Manufacturing Overhead Applied $35,000 Work in Process Inventory $5,425 Manufacturing Overhead Incurred $29,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete,...
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory $3,800 Manufacturing Overhead Applied $34,900 Work in Process Inventory $5,775 Manufacturing Overhead Incurred $30,800 Subsidiary data for Work in Process Inventory on June 1 are as follows. Job Cost Sheets Customer Job Cost Element Rodgers Stevens Linton Direct materials...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT