Question

In: Operations Management

Consider the following table of activities A through E in which A is the start node...

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday). All activities require the same resource. Assume no working-day holidays during the months of May and June—no Memorial Day holiday, for example.

Activity Duration (days) Predecessor
A 5 --
B 5 A
C 10 A
D 4 A
E 5 B, C, D


On a piece of scratch paper, draw the early-start Gantt Chart associated with this table. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Given that the Month of May has 31 days, what would be the completion date for the project?

  • Monday, June 8, 2020

  • Wednesday, June 10, 2020

  • Friday, June 5, 2020

  • Thursday, June 11, 2020

  • Thursday, June 4, 2020

Solutions

Expert Solution

ANSWER: Thursday, June 11, 2020

------------------------------------------------

Explanation:

Gantt chart based on Early Start and Finish times is following:

In the above Gantt chart, we see that there is resource over-load in periods 6 to 10

Resource over-load is because activities B,C,D are scheduled to start on the same day and occur concurrently.

We need to schedule them sequentially

Resulting Gantt chart is following:

Total number of working days to complete the project = 29 working days

Considering 5 working days per week and starting date of May 4, 2020

Completion date is:

Thursday, June 11, 2020


Related Solutions

Consider the following contingency table of observed frequencies. Complete parts a. through e. below. Column Variable...
Consider the following contingency table of observed frequencies. Complete parts a. through e. below. Column Variable Row Variable Upper C 1C1 Upper C 2C2 Upper C 3C3 Upper R 1R1 2020 77 1818 Upper R 2R2 88 88 1313 Upper R 3R3 88 1616 6 Click the icon to view the contingency table.a. Identify the null and alternative hypotheses for a​ chi-square test of independence based on the information in the table. This test will have a significance level of...
Consider the following payoff table in which D1 through D3 represent decision alternatives, S1 through S4...
Consider the following payoff table in which D1 through D3 represent decision alternatives, S1 through S4 represent states of nature, and the values in the cells represent return on investments in millions.     S1 S2 S3 S4 D1 30 20 -50 100 D2 60 150 40 -80 D3 40 10 80 80 What are the decision alternatives, and what are the chance events for this problem? Construct a decision tree What is the preferred alternative when the decision maker is...
Consider the following table definitions create table node( node_id integer primary key, node_color varchar(10)); create table...
Consider the following table definitions create table node( node_id integer primary key, node_color varchar(10)); create table edge( edge_id integer primary key, origin_id integer, destination_id integer, foreign key (origin_id) references node(node_id), foreign key (destination_id) references node(node_id)); What is the result of the following query? select node_id, node_color, destination_id from node, edge; An inner join of the tables node and edge that lists origin node_id and node_color together with the node_id of the destination node for all those nodes that have outgoing...
Consider an unweighted, undirected graph G = <V, E>. The neighbourhood of a node v ∈...
Consider an unweighted, undirected graph G = <V, E>. The neighbourhood of a node v ∈ V in the graph is the set of all nodes that are adjacent (or directly connected) to v. Subsequently, we can define the neighbourhood degree of the node v as the sum of the degrees of all its neighbours (those nodes that are directly connects to v). (a) Design an algorithm that returns a list containing the neighbourhood degree for each node v ∈...
Which of the following expenditure cycle activities can be eliminated through the use of IT or...
Which of the following expenditure cycle activities can be eliminated through the use of IT or reengineering? ordering goods receiving goods approving vendor invoices cash disbursements Which   of   the   following   revenue   cycle   activities   can   potentially   be eliminated by technology? sales order entry shipping cash collections billing Which of the following matches is performed in evaluated receipt settlement (ERS)? the vendor invoice with the receiving report the purchase order with the receiving report the vendor invoice with the purchase order the...
Consider the following struct that represents a node within a binary tree: struct Node { int...
Consider the following struct that represents a node within a binary tree: struct Node { int data; // Data of interest Node *left // Link to left subtree (nullptr if none) Node *right ; // Link to right subtree (nullptr if none) }; Complete the following function that computes the number of elements in a binary tree: // Counts the number of elements in the binary tree to which t points. // Returns the number of elements. int size(Node *t)...
Match each of the following transactions to the journal (a through e) in which it would...
Match each of the following transactions to the journal (a through e) in which it would be entered. Rendered services on account Drag answer here Received payment from customer on account Drag answer here Received cash from the bank in exchange for a note payable Drag answer here Purchased supplies on account Drag answer here Paid vendor on account Drag answer here Withdrew cash for personal use (by owner) Drag answer here Withdrew supplies from the business for personal use...
If you were going to start an e-business what types of activities would you outsource (outside...
If you were going to start an e-business what types of activities would you outsource (outside of the company, not necessarily outside of the country)? Be sure to explain your reasoning.
Consider the debt ratio. Which of the following activities will decrease the debt ratio? a. purchasing...
Consider the debt ratio. Which of the following activities will decrease the debt ratio? a. purchasing treasury stock with cash b. selling common stock for cash c. selling inventory for cash d. purchasing inventory with cash
For each E coli genotype and condition in the following table, choose which sets of functional...
For each E coli genotype and condition in the following table, choose which sets of functional proteins will or will not be produced. All grown in media with no/low glucose. IS indicates a super-repressor (it can’t bind to lactose/inducers). OC indicates a constitutive operon (no repressor can bind to this region of DNA). I- ; Z- ; Y-each indicate an allele that does not produce a functional protein. P- indicates a mutation in the promoter region such that RNA polymerase...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT