In: Accounting
The Bennett Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Bennett uses normal costing with two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department with machine-hours as the allocation base and the finishing department with direct manufacturing labor costs as the allocationbase). The 2017 budget for the plant is as follows:
Machining Department | Finishing Department | |
Manufacturing overhead costs | $ 9,065,000 | $ 8,058,000 |
Direct manufacturing labor costs | $ 950,000 | $ 3,950,000 |
Direct manufacturing labor-hours | 32,000 | 145,000 |
Machine-hours | 185,000 | 35,000 |
Question:
1. Identify the components of the overview diagram of Bennett's job-costing system.
2. What is the budgeted manufacturing overhead rate in the machining department? In the finishingdepartment?
3. During the month of January, the job-cost record for Job 431 shows the following:
Machining Department | Finishing Department | |
Direct materials used | $ 14,500 | $ 4,000 |
Direct manufacturing labor costs | $ 800 | $ 1,400 |
Direct manufacturing labor-hours | 20 | 70 |
Machine-hours | 100 | 15 |
Compute the total manufacturing overhead cost allocated to Job 431.
4. Assuming that Job 431 consisted of 100 units of product, what is the cost per unit?
5. Amounts at the end of 2017 are as follows:
Machining Department | Finishing Department | |
Manufacturing overhead incurred | $ 12,010,000 | $ 9,184,000 |
Direct manufacturing labor costs | $ 980,000 | $ 4,600,000 |
Machine-hours | 240,000 | 33,0000 |
Compute the under- or overallocated manufacturing overhead for each department and for the Dover plant as a whole.
6. Why might Bennett use two different manufacturing overhead cost pools in its job-costing system?
2 | Budgeted manufacturing overhead rate : | |||
In Machining Department = Manufacturing overhead cost / Machine hrs | ||||
$9065000 /185,000 = $49 per machine hour | ||||
In Finishing Department = Manufacturing overhead cost / Direct Manufacturing labor cost | ||||
$8,058000 / $3950,000 = 2.04 | ||||
3). | Machining Department overhead = $20 per machine hr * 100 hrs = $2000 | |||
Finishing Department overhead = $1400 * 204% = $2856 | ||||
Total manufacturing overhead = $4856 | ||||
4). | Total costs of Job 431: | |||
Direct material - Machining Department = $14500 | ||||
- Finishing Department = $4000 | ||||
Direct manufacturing labor - Machining Department = $800 | ||||
- Finishing Department = $1400 | ||||
Manufacturing overhead = $4856 | ||||
Total Cost = $25556 | ||||
Cost per unit = $25556 / 100 = $255.56 | ||||
5 | ||||
Actual manufacturing overhead | machining | finishing | ||
Actual manufacturing overhead | $12,010,000 | $9,184,000 | ||
Manufacturing overhead allocated | $11,760,000 | $9,384,000 | ||
($49×240,000) | (204%×4600,000) | |||
Under allocated(over allocated) | $250,000 | $ (200,000.00) | ||
For plant as whole: | ||||
(12,010,000+$9184,000)-(11760,000+$9384,000) | ||||
50000 Under applied. | ||||
6 | In machining department main focal points is machines , so machine hours is selected for this.In finishing department, labor cost is key area.so it is selected by the company .In both department key area is different so different cost drivers are selected for both departments. |