Question

In: Accounting

Merrill Corp. has the following information available about a potential capital investment:    Initial Investment 1,700,000 Annual...

Merrill Corp. has the following information available about a potential capital investment:   

Initial Investment 1,700,000
Annual Net income 190,000
Expected Life 8 years
Salvage Value 250,000
Merills Cost of Capital 10%

Assume straight line depreciation method is used.

Required:

1. Calculate the project’s net present value.

2. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 10 percent.

3. Calculate the net present value using a 15 percent discount rate.

4. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 15 percent.

NET PRESENT VALUE IS NOT 397,220

Solutions

Expert Solution

Initial Investment = $1,700,000
Salvage Value = $250,000
Useful Life = 8 years

Annual Depreciation = (Initial Investment - Salvage Value) / Useful Life
Annual Depreciation = ($1,700,000 - $250,000) / 8
Annual Depreciation = $181,250

Annual Net Cash Flow = Annual Net Income + Annual Depreciation
Annual Net Cash Flow = $190,000 + $181,250
Annual Net Cash Flow = $371,250

Answer 1.

Cost of Capital = 10%

Net Present Value = -$1,700,000 + $371,250 * PVA of $1 (10%, 8) + $250,000 * PV of $1 (10%, 8)
Net Present Value = -$1,700,000 + $371,250 * 5.3349 + $250,000 * 0.4665
Net Present Value = $397,206.63 or $397,207

Answer 2.

Internal rate of return is higher than 10% as NPV is positive at cost of capital of 10%.

Answer 3.

Cost of Capital = 15%

Net Present Value = -$1,700,000 + $371,250 * PVA of $1 (15%, 8) + $250,000 * PV of $1 (15%, 8)
Net Present Value = -$1,700,000 + $371,250 * 4.4873 + $250,000 * 0.3269
Net Present Value = $47,635.13 or $47,635

Answer 4.

Internal rate of return is higher than 15% as NPV is positive at cost of capital of 15%.


Related Solutions

Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,800,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,800,000 Annual net income $ 200,000 Expected life 8 years Salvage value $ 240,000 Merrill’s cost of capital 10 % Assume straight line depreciation method is used. Required: 1. Calculate the project’s net present value. 2. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 10 percent. 3. Calculate the net present value using a 15 percent...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 900,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 900,000 Annual net income $ 90,000 Expected life 8 years Salvage value $ 100,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000 Annual net income $ 110,000 Expected life 8 years Salvage value $ 120,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 800,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 800,000 Annual net income $ 80,000 Expected life 8 years Salvage value $ 90,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used. Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,200,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,200,000 Annual net income $ 120,000 Expected life 8 years Salvage value $ 130,000 Merrill’s cost of capital 10 % Assume straight line depreciation method is used. Required: 1. Calculate the project’s net present value. 2. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 10 percent. 3. Calculate the net present value using a 13 percent...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 700,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 700,000 Annual net income $ 70,000 Expected life 8 years Salvage value $ 80,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment: Initial investment $ 2,200,000...
Merrill Corp. has the following information available about a potential capital investment: Initial investment $ 2,200,000 Annual net income $ 190,000 Expected life 8 years Salvage value $ 200,000 Merrill’s cost of capital 8 % Assume straight line depreciation method is used. Required: 1. Calculate the project’s net present value. 2. Without making any calculations, determine whether the internal rate of return (IRR) is more or less than 8 percent. 3. Calculate the net present value using a 12 percent...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 2,400,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 2,400,000 Annual net income $ 170,000 Expected life 8 years Salvage value $ 180,000 Merrill’s cost of capital 8 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 2,600,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 2,600,000 Annual net income $ 150,000 Expected life 8 years Salvage value $ 160,000 Merrill’s cost of capital 6 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000...
Merrill Corp. has the following information available about a potential capital investment:    Initial investment $ 1,100,000 Annual net income $ 110,000 Expected life 8 years Salvage value $ 120,000 Merrill’s cost of capital 7 % Assume straight line depreciation method is used.   Required: 1. Calculate the project’s net present value. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Do not round intermediate calculations....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT