In: Finance
Merrill Corp. has the following information available about a potential capital investment:
Initial investment | $ | 700,000 | |||||
Annual net income | $ | 70,000 | |||||
Expected life | 8 | years | |||||
Salvage value | $ | 80,000 | |||||
Merrill’s cost of capital | 7 | % | |||||
Assume straight line depreciation method is used.
Required:
1. Calculate the project’s net present value. (Future
Value of $1, Present Value of $1, Future Value Annuity of $1,
Present Value Annuity of $1.) (Use appropriate factor(s)
from the tables provided. Do not round intermediate calculations.
Round the final answer to nearest whole dollar.)
1a. Without making any calculations, determine
whether the internal rate of return (IRR) is more or less than 7
percent.
Less than 7 Percent | |
Greater than 7 Percent |
1b. Calculate the net present value using a 14
percent discount rate. (Future Value of $1, Present Value of $1,
Future Value Annuity of $1, Present Value Annuity of $1.)
(Use appropriate factor(s) from the tables provided. Do not
round intermediate calculations. Round the final answer to nearest
whole dollar.)
1c. Without making any calculations, determine
whether the internal rate of return (IRR) is more or less than 14
percent.
More than 14 percent | |
Less than 14 percent | |
Equal to 14 percent |
Answer 1 | |||||||||||
Calculation of the project’s net present value. | |||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | NPV | |
Initial Investment | -$700,000.00 | ||||||||||
Annual net income | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | |||
Depreciation | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | |||
Salvage value | $80,000.00 | ||||||||||
Net Cash flow | -$700,000.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $227,500.00 | ||
x Discount factor @ 7% | 1 | 0.93458 | 0.87344 | 0.81630 | 0.76290 | 0.71299 | 0.66634 | 0.62275 | 0.58201 | ||
Present Values | -$700,000.00 | $137,850.47 | $128,832.21 | $120,403.94 | $112,527.04 | $105,165.46 | $98,285.48 | $91,855.59 | $132,407.07 | $227,327.258 | |
Net present value = | $227,327.258 | ||||||||||
Depreciation per year using straight line method = ($700000-$80000)/8 years = $77,500 | |||||||||||
Answer 2 | |||||||||||
As the NPV of the project is positive at 7% discount rate , it is concluded that IRR of the project is greater than 7%. | |||||||||||
Answer 3 | |||||||||||
Calculation of the project’s net present value. | |||||||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | NPV | |
Initial Investment | -$700,000.00 | ||||||||||
Annual net income | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | $70,000.00 | |||
Depreciation | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | $77,500.00 | |||
Salvage value | $80,000.00 | ||||||||||
Net Cash flow | -$700,000.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $147,500.00 | $227,500.00 | ||
x Discount factor @ 14% | 1 | 0.87719 | 0.76947 | 0.67497 | 0.59208 | 0.51937 | 0.45559 | 0.39964 | 0.35056 | ||
Present Values | -$700,000.00 | $129,385.96 | $113,496.46 | $99,558.30 | $87,331.84 | $76,606.88 | $67,199.02 | $58,946.51 | $79,752.18 | $12,277 | |
Net present value = | $12,277 | ||||||||||
Answer 4 | |||||||||||
As the NPV of the project is positive at 14% discount rate , it is concluded that IRR of the project is greater than 14% | |||||||||||