In: Operations Management
Completed
| 
 Activity  | 
 Pre  | 
 Time (Days)  | 
 ES  | 
 LS  | 
 LS  | 
 LF  | 
 Critical  | 
 Slack  | 
|
| 
 A  | 
 Select An Area  | 
 NA  | 
 10  | 
 0  | 
 10  | 
 0  | 
 10  | 
 Yes  | 
 0  | 
| 
 B  | 
 Furnish the land  | 
 A  | 
 30  | 
 10  | 
 40  | 
 10  | 
 40  | 
 Yes  | 
 0  | 
| 
 C  | 
 Select Equipment  | 
 A  | 
 5  | 
 10  | 
 15  | 
 52  | 
 57  | 
 42  | 
|
| 
 D  | 
 Make Designs  | 
 B, C  | 
 10  | 
 40  | 
 50  | 
 40  | 
 50  | 
 Yes  | 
 0  | 
| 
 E  | 
 Get Equipment  | 
 C  | 
 3  | 
 15  | 
 18  | 
 57  | 
 60  | 
 42  | 
|
| 
 F  | 
 Recruit Workforce  | 
 D  | 
 10  | 
 50  | 
 60  | 
 50  | 
 60  | 
 Yes  | 
 0  | 
| 
 G  | 
 Assign task  | 
 E, F  | 
 3  | 
 60  | 
 63  | 
 60  | 
 63  | 
 Yes  | 
 0  | 
| 
 H  | 
 Give Workers a time frame  | 
 G  | 
 2  | 
 63  | 
 65  | 
 63  | 
 65  | 
 Yes  | 
 0  | 
| 
 I  | 
 Start Work  | 
 H  | 
 2  | 
 65  | 
 67  | 
 65  | 
 67  | 
 Yes  | 
 0  | 
| 
 J  | 
 Check on Progress  | 
 I  | 
 60  | 
 67  | 
 127  | 
 67  | 
 127  | 
 Yes  | 
 0  | 
| 
 K  | 
 Finish Playground  | 
 J  | 
 20  | 
 127  | 
 147  | 
 127  | 
 147  | 
 Yes  | 
 0  | 
Needs to be completed