In: Operations Management
Completed
Activity |
Pre |
Time (Days) |
ES |
LS |
LS |
LF |
Critical |
Slack |
|
A |
Select An Area |
NA |
10 |
0 |
10 |
0 |
10 |
Yes |
0 |
B |
Furnish the land |
A |
30 |
10 |
40 |
10 |
40 |
Yes |
0 |
C |
Select Equipment |
A |
5 |
10 |
15 |
52 |
57 |
42 |
|
D |
Make Designs |
B, C |
10 |
40 |
50 |
40 |
50 |
Yes |
0 |
E |
Get Equipment |
C |
3 |
15 |
18 |
57 |
60 |
42 |
|
F |
Recruit Workforce |
D |
10 |
50 |
60 |
50 |
60 |
Yes |
0 |
G |
Assign task |
E, F |
3 |
60 |
63 |
60 |
63 |
Yes |
0 |
H |
Give Workers a time frame |
G |
2 |
63 |
65 |
63 |
65 |
Yes |
0 |
I |
Start Work |
H |
2 |
65 |
67 |
65 |
67 |
Yes |
0 |
J |
Check on Progress |
I |
60 |
67 |
127 |
67 |
127 |
Yes |
0 |
K |
Finish Playground |
J |
20 |
127 |
147 |
127 |
147 |
Yes |
0 |
Needs to be completed