In: Mechanical Engineering
Calculate the takt given the following information: ? Two shifts at 8 hours each shift ? Two 10-minute breaks per shift ? 25 minute lunchtime per shift ? There are a total of 8 holidays per year ? Normal work schedule is 5 days per week (Monday-Friday) ? Customer contract calls for 450,000 units/year (contractual agreement) You must show ALL your work/calculations in order to get full credit!