Question

In: Operations Management

Kelson Sporting Equipment, Inc., makes two different models of baseball gloves: a regular glove and a...

Kelson Sporting Equipment, Inc., makes two different models of baseball gloves: a regular glove and a catcher’s mitt. The firm has 1000 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 100 hours available in its packaging and shipping department. The production time requirements and the profit contribution for each product are:

Production Time (hours)

Model

Cutting and Sewing

Finishing

Packaging and Shipping

Profit/Glove

Regular glove

1

1/2

1/8

$6

Catcher's unit

3/2

1/3

1/4

$9

Assume that the company is interested in maximizing the total profit contribution.

  1. Formulate a mathematical model for this problem.
  2. How many gloves of each model should Kelson manufacture?
  3. What is the total profit contribution Kelson can earn with the above production quantities?
  4. How many hours of production time will be scheduled in each department?

Solutions

Expert Solution

Note: All the parts have been done in the attached images. If you're satisfied with the answer, do rate. In case of any doubt, please mention in the comment section. Thank you.


Related Solutions

Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 400 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 200 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging and Shipping Profit/Glove Regular model...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 700 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 200 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging and Shipping Profit/Glove Regular model...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 800 hours of production time available in its cutting and sewing department, 150 hours available in its finishing department, and 400 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging and Shipping Profit/Glove Regular model...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 800 hours of production time available in its cutting and sewing department, 150 hours available in its finishing department, and 400 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging and Shipping Profit/Glove Regular model...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 900 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 200 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging and Shipping Profit/Glove Regular model...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a...
Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher’s model. The firm has 900 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 100 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (hours)   Model   Cutting and Sewing Finishing   Packaging and Shipping Profit/Glove   Regular model...
use Excel Screen shot Pleaseeeee Kelson Sporting Equipment, Inc., makes two different types of baseball gloves:...
use Excel Screen shot Pleaseeeee Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher's model. The firm has 900 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 100 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: Production Time (Hours) Model Cutting and Sewing Finishing Packaging...
please show if this is done in excel, Kelson Sporting Equipment, Inc., makes two different types...
please show if this is done in excel, Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a catcher’s model. The firm has 900 hours of production time available in its cutting and sewing department, 300 hours available in its finishing department, and 100 hours available in its packaging and shipping department. The production time requirements and the profit contribution per glove are given in the following table: PRODUCTION TIME HOURS Model Cutting and...
Little League, Inc. makes two kinds of baseball gloves - the Beginner and the Pro. Below...
Little League, Inc. makes two kinds of baseball gloves - the Beginner and the Pro. Below is some relevant information for the past year (unit means one baseball glove):   Beginner Pro Number of units sold 65,000 10,000 Sales price per unit $65 $100 Direct materials per unit $10 $20 Direct labor dollars per unit $30 $45 Cutting machine-hours per unit 0.50 1.00 Direct labor-hours per unit 2.00 3.00 Little League is considering the use of activity-based costing, although it currently...
Refer to the Kelson Sporting Equipment problem (Chapter 7, Problem 24). Letting R number of regular...
Refer to the Kelson Sporting Equipment problem (Chapter 7, Problem 24). Letting R number of regular gloves C number of catcher’s mitts leads to the following formulation: The sensitivity report is shown in Figure 8.14. a. What is the optimal solution, and what is the value of the total profit contribution? b. Which constraints are binding? c. What are the shadow prices for the resources? Interpret each. d. If overtime can be scheduled in one of the departments, where would...