In: Accounting
I need 450 words.
Explain why the NPV of a relatively long-term project, defined as one for which a high percentage of its cash flows are expected in the distant future, is more sensitive to changes in the required rate of return than is the NPV of a short-term project. In addition, please provide an example to better demonstrate your explanation.
The reason for the phenomenon is the nature of compounding. | ||
The formula for discounting of a cash flow is: | ||
Cash flow/(1+r)^t | ||
where | ||
r = discount rate per period, and | ||
t = number of the year [1,2,3 etc]. | ||
The value of CF/(1+i)^t decreases more than proportionately | ||
[in geometric proportion] as t increases, which means that the | ||
cash flows in the later years are discounted more heavily than | ||
the earlier years. This being so, any change in interest rates | ||
affects the value of the later cash flows more. | ||
Example: | ||
Consider two projects with cash flows as below; | ||
A = -10000, 2000, 3000, 3000, 5000, 5000 | ||
B = -10000, 9000,9000 | ||
The NPVs with 10% discount rate are: | % Change | |
A = -10000+ 2000/1.1+3000/1.1^2+3000/1.1^3+5000/1.1^4+5000/1.1^5= | $ 3,071.14 | |
B = -10000+9000/1.1+9000/1.1^2 = | $ 5,619.83 | |
The NPVs with 12% discount rate are: | ||
A = -10000+ 2000/1.12+3000/1.12^2+3000/1.12^3+5000/1.12^4+5000/1.12^5= | $ 2,327.36 | -24.22% |
B = -10000+9000/1.12+9000/1.12^2 = | $ 5,210.46 | -7.28% |
As can be seen Project A's NPV is affected to a larger % for a 2% change in | ||
discount rate in comparison with the % change in the NPV of Project B. |