In: Accounting
Traditional Product Costing Versus Activity-Based Costing
High Country Outfitters, Inc., makes backpacks for large sporting
goods chains that are sold under the customers' store brand names.
The accounting department has identified the following overhead
costs and cost drivers for next year:
Overhead Item | Expected Costs |
Cost Driver |
Maximum Quantity |
---|---|---|---|
Setup costs |
$1,404,000 |
Number of setups |
7,200 |
Ordering costs |
360,000 |
Number of orders |
60,000 |
Maintenance |
1,200,000 |
Number of machine hours | 80,000 |
Power |
120,000 |
Number of kilowatt hours |
600,000 |
Total predicted direct labor hours for next year is 60,000. The following data are for two recently completed jobs:
Job 201 | Job 202 | |
---|---|---|
Cost of direct materials | $18,500 | $20,000 |
Cost of direct labor | $24,125 | $76,250 |
Number of units completed | 1,125 | 915 |
Number of direct labor hours | 270 | 330 |
Number of setups | 18 | 22 |
Number of orders | 24 | 45 |
Number of machine hours | 540 | 450 |
Number of kilowatt hours | 270 | 360 |
a. Determine the unit cost for each job using a traditional
company-wide overhead rate based on direct labor hours.
Round rate to two decimal places.
Overhead rate per direct labor hour $Answer
Use rounded overhead rate calculated above for calculations below.
Round cost answers to the nearest whole number, when needed. Round
cost per unit to two decimal places, if needed.
Job 201 | Job 202 | |
---|---|---|
Direct materials | $Answer | $Answer |
Direct labor | Answer | Answer |
Overhead | Answer | Answer |
Total job cost | Answer | Answer |
Units | Answer | Answer |
Per unit cost | $Answer | $Answer |
b. Determine the unit cost for each job using ABC. Activity-based overhead rates:
Round cost answers to the nearest whole number, when needed.
Round cost per unit to two decimal places, if needed.
Setup costs |
$Answer per setup |
Ordering costs |
$Answer per order |
Maintenance costs | $Answer per machine hour |
Power |
$Answer per kwh |
Job 201 | Job 202 | |
---|---|---|
Direct materials | $Answer | $Answer |
Direct labor | Answer | Answer |
Overhead | ||
Setup cost | Answer | Answer |
Ordering costs | Answer | Answer |
Maintenance costs | Answer | Answer |
Power | Answer | Answer |
Total job costs | $Answer | $Answer |
Units produced | Answer | Answer |
Cost per unit | $Answer | $Answer |
total estimated overhea | |||||||
Setup costs | 1,404,000 | ||||||
ordering costs | 360,000 | ||||||
maintenance | 1,200,000 | ||||||
power | 120,000 | ||||||
total estimated overhead | 3,084,000 | ||||||
a. | overhead rate = estimated overhead/estimated direct hours | ||||||
3084,000/60,000 | |||||||
51.4 | |||||||
overhead rate per direct labor hour | 51.4 | ||||||
Job 201 | job 202 | ||||||
Cost of direct materials | 18,500 | 20,000 | |||||
cost of direct labor | 24,125 | 76,250 | |||||
overhead (270*51.4);(330*51.4) | 13878 | 16962 | |||||
total job cost | 56,503 | 113,212 | |||||
units | 1,125 | 915 | |||||
per unit cost | 50.22 | 123.73 | |||||
b) | Setup costs | (1,404,000/7200)= | 195 | per setup | |||
ordering costs | (360,000/60,000)= | 6 | per order | ||||
maintenance costs | (1,200,000/80,000)= | 15 | per MH's | ||||
power | (120,000/600,000)= | 0.2 | per KWH | ||||
Job 201 | job 202 | ||||||
Cost of direct materials | 18,500 | 20,000 | |||||
cost of direct labor | 24,125 | 76,250 | |||||
overhead | |||||||
Setup costs(195*18);(195*22) | 3510 | 4290 | |||||
ordering costs(6*24);(6*45) | 144 | 270 | |||||
maintenace (15*540);(15*450) | 8100 | 6750 | |||||
power (.2*270);(.2*360) | 54 | 72 | |||||
total job costs | 54,433 | 107,632 | |||||
units | 1,125 | 915 | |||||
per unit cost | 48.38 | 117.63 | |||||