Question

In: Finance

1. Sunk costs- Costs that have accrued in the past. Example: An organization has a project...

1. Sunk costs- Costs that have accrued in the past. Example: An organization has a project with an initial budget of $2,000,0000. The project is half complete and has spent $3,000,000. Should the organization consider the fact that it is already $1,000,000 over budget when determining whether to continue with the project?

2. A five-year project has an initial fixed asset investment of $600,600, an initial net working capital investment of $21,000, and an annual operating cash flow of –$75,400. The fixed asset is fully depreciated over the life of the project and has no salvage value. The net working capital will be recovered when the project ends. The required return is 11 percent. What is the project's equivalent annual cost, or EAC?

A

−$248,092.76

B

−$182,309.18

C

−$246,586.50

D

−$321,929.36

E

−$240,214.53

3.Ethics Issues

In an L.A. Law episode, an automobile manufacturer knowingly built cars that had a significant safety flaw.

Rather than redesigning the cars (at substantial additional cost), the manufacturer calculated the expected costs of future lawsuits and determined that it would be cheaper to sell an unsafe car and defend itself against lawsuits than to redesign the car.

What issues does the financial analysis overlook?

4.Fill in the Blanks

A $1,000,000 investment is depreciated using a seven-year MACRS class life.

It requires $150,000 in additional inventory and will increase accounts payable by $50,000.

It will generate $400,000 in revenue and $150,000 in cash expenses annually, and the tax rate is 40%.

What is the incremental cash flow in years 0,

Year 1

Year 7

Year 8?

Solutions

Expert Solution

1) Sunk cost are those which are already spent. They are irrelevant while deciding future cash flow and thus they should be ignore while deciding whether the project should be undertaken or not..Thus $1,000,000 that is spent extra should be ignored when determining whether to continue with project or not

2) Statement showing EAC

Particulars Amount
Initial investment in fixed asset -600600
Initial net working capital -21000
Present value of WC recovered at end of year 5(note 1) 12462
PV of total cost -609138
PVIFA(11%,5years) 3.6959
Equalised cost(PV of total cost/PVIFA) -164814
Annual operating cash flow -75400
equivalent annual cost, or EAC -240214

Note 1 : WC at year 5 * PVIF(11%,5)

=21000*0.59345

=12462$

3) Financial analysis only helps to decide whether the project should be taken or not only on basis of financial information given. It ignores the non financial information such as ethics. In given case selling unsafe car with possible law suits are financially viable but are not ethical

4)

First of all we need to find depreciation for all years

Year Opening balance Depreciation rate Depreciation = 1000,000*Depreciation rates Closing balance
1 1,000,000 14.29% 142900 857,100
2 857,100 24.49% 244900 612,200
3 612,200 17.49% 174900 437,300
4 437,300 12.49% 124900 312,400
5 312,400 8.93% 89300 223,100
6 223,100 8.92% 89200 133,900
7 133,900 8.93% 89300 44,600
8 44,600 4.46% 44600 0

Statement showing incremental cash flow

Paticulars 0 1 2 3 4 5 6 7 8
Initial Investment -1000000
WC Requirement (1,50,000-50,000) -100000
Revenue 400000 400000 400000 400000 400000 400000 400000 400000
Expense -150000 -150000 -150000 -150000 -150000 -150000 -150000 -150000
Depreciation -142900 -244900 -174900 -124900 -89300 -89200 -89300 -44600
PBT 107100 5100 75100 125100 160700 160800 160700 205400
Tax @ 40% 42840 2040 30040 50040 64280 64320 64280 82160
PAT 64260 3060 45060 75060 96420 96480 96420 123240
Add Depreciation 142900 244900 174900 124900 89300 89200 89300 44600
Annual cash flow 207160 247960 219960 199960 185720 185680 185720 167840
Total cash flow -1100000 207160 247960 219960 199960 185720 185680 185720 167840

Thus for year 0 is -1100,000$

Year 1 = 207160$

Year 7 = 185720$

Year 8 = 167840$


Related Solutions

Topic: Sunk Costs a. If you have invested money into a project, but the remainder of...
Topic: Sunk Costs a. If you have invested money into a project, but the remainder of the project has a negative npv, what should you do? should you continue the project? discuss your course of action relating to the topic stated above. b. You have been given a project proposal. The project is expected to finish in five years (year 5) and has a cost of capital of 10%. If the initial costs of equipment is $400,000, the additional anticipated...
1. Identify relevant costs, irrelevant costs, and sunk costs. Give an example of each. 2. In...
1. Identify relevant costs, irrelevant costs, and sunk costs. Give an example of each. 2. In 150 words or fewer, explain the difference between relevant costs, irrelevant costs, and sunk costs.
1. Which of the following statements is most CORRECT regarding sunk costs? A) An example of...
1. Which of the following statements is most CORRECT regarding sunk costs? A) An example of a sunk cost is the cost associated with restoring the site of a strip mine once the ore has been depleted B) Sunk costs must be considered if the IRR method is used but if not the firm relies on the NPV method C) A good example of a sunk cost is money that a banking corporation spent last year to investigate the site...
Explain sunk costs and opportunity costs. Provide a business example for each of these terms.
Explain sunk costs and opportunity costs. Provide a business example for each of these terms.
Find the best match A. Sunk costs B. Relevant cost C. Opportunity cost Past costs that...
Find the best match A. Sunk costs B. Relevant cost C. Opportunity cost Past costs that are not relevant John is considering buying new machines because last year he spent $4000 on machines that won’t work the $4000 is a John can invest or he can leave his money in the bank and earn $4000 in interest the $4000 is a Fixed cost or $10,000 variable costs are $40 per unit for decision makeing purposes the $40 is the
1) Making rent payments in advance is an example of a(n): A) Accrued revenue. B) Accrued...
1) Making rent payments in advance is an example of a(n): A) Accrued revenue. B) Accrued expense. C) Deferred revenue. D) Prepaid expense. 2) A company purchased $270,000 in supplies during the year. The supplies account increased by $10,000 during the year to an ending balance of $66,000. For what amount was the adjusting entry to supplies expense? A) $300,000. B) $280,000. C) $260,000. D) $240,000.
WEEK 5: RELEVANT COSTS What is an example of an opportunity cost? How about a sunk...
WEEK 5: RELEVANT COSTS What is an example of an opportunity cost? How about a sunk cost? Are either of these relevant? Avoidable? Examples from work would be great!
Why should sunk costs be ignored for decision making? Give an example of why it makes...
Why should sunk costs be ignored for decision making? Give an example of why it makes sense to ignore sunk costs and why it is often difficult to do so.
Which is the individual difficulty that sunk costs, opportunity costs, side effects and allocated costs has...
Which is the individual difficulty that sunk costs, opportunity costs, side effects and allocated costs has in determining incremental cash flows
What are sunk costs? Give an example from your own experience. Please include resources.
What are sunk costs? Give an example from your own experience. Please include resources.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT