A CAT D&H (power-shift) dozer is used to push material that weights 87 pcf in the...

A CAT D&H (power-shift) dozer is used to push material that weights 87 pcf in the bank state. It is estimated that the material will swell 5% from a bank state. The material is in a loose stock pile and is to be moved an average distance of 250 ft on a 2% downhill grade. The operator is average. Job efficiency is estimated to be at a 50-min hour. Assume that the dozer will have an 0.39 coefficient of traction. The O&O cost for the dozer is $86 per hour and the operator's wage is $17.50 per hour plus 44% for fringes, insurance and worker's compensation. Calculate the production in bcy per hour. (Reference Table 7.2 and Figure 7.13)

TABLE 7.2 Caterpillar job condition correction factors for estimating dozer production
Track-type tractor Wheel-type tractor
Operator
Excellent 1.00 1.00
Average 0.75 0.60
Poor 0.60 0.50
Material
Loose stockpile 1.20 1.20
Hard to cut; frozen
with tilt cylinder 0.80 0.75
without tilt cylinder 0.70 —
cable-controlled blade 0.60 —
Hard to drift; “dead” (dry, noncohesive 0.80 0.80
material) or very sticky material
Rock, ripped or blasted 0.60–0.80 —
Slot dozing 1.20 1.20
Side-by-side dozing 1.15–1.25 1.15–1.25
Visibility
Dust, rain, snow, fog, or darkness 0.80 0.70
Job efficiency
50 min/hr 0.83 0.83
40 min/hr 0.67 0.67
Direct-drive transmission
(0.1-min fixed time) 0.80 —
Bulldozer*
Adjust based on SAE capacity relative
to the base blade used in the estimated
dozing production graphs
Grades—see the graph

Solutions

Expert Solution


Related Solutions

A CAT D7G power shift tracklaying dozer is used in a pushing operation. The dozer is...
A CAT D7G power shift tracklaying dozer is used in a pushing operation. The dozer is equipped with a straight 7U blade. The material (dry and noncohesive) weighs 100 pcf in the bank state. It is estimated that the material will swell 4% from bank to loose state. The center-of-mass-to-center-ofmass pushing is 250 ft on a 0% grade. The operator will have excellent skill, the job will be performed in good conditions. Job efficiency can be assumed to be equivalent...
A CAT 834 (power-shift, wheel-type) dozer is used in a pushing operation. The dozer is equipped...
A CAT 834 (power-shift, wheel-type) dozer is used in a pushing operation. The dozer is equipped with a straight blade. The material is in a loose stock pile and weighs 80 pcf in the bank state. It is estimated that the material will swell 4 % from bank to loose state. The center-of-mass-to center of mass pushing is 250 ft on a 0% grade. The operators have average skill and the job will be performed in normal conditions. Job efficiency...
A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with...
A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with a straight blade. The material (dry and noncohesive) weighs 98 pcf in the bank state. It is estimated the material will swell 6%, from bank to loose state. The center-of mass–to–center-of-mass pushing distance is 200 ft. Job efficiency can be assumed to be equivalent to a 45-min hour. Calculate the production in bcy per hour and the direct cost of the proposed earthmoving operation...
A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with...
A 240 hp (power-shift) dozer is used in a pushing operation. The dozer is equipped with a straight blade. The material (dry and noncohesive) weighs 98 pcf in the bank state. It is estimated the material will swell 6%, from bank to loose state. The center-of mass-to-center-of-mass pushing distance is 200 ft. Job efficiency can be assumed to be equivalent to a 45-min hour. Calculate the production in bey per hour and the direct cost of the proposed earthmoving operation...
1. A contractor is planning to use a crawler tractor with power shift transmission to push...
1. A contractor is planning to use a crawler tractor with power shift transmission to push 1,500 LCY. The tractor must haul the loose material up a 12% slope where it will be stockpiled for later removal. The contractor has measured the tractor blade load measurement: the pile length 12.6 ft, the pile width 8.1 ft, and the pile height 4 ft. The tractor weighs 44,400 pounds, and the coefficient of traction is estimated to be 0.7. The average haul...
An inductor used in a dc power supply has an inductance of 11.0 H and a...
An inductor used in a dc power supply has an inductance of 11.0 H and a resistance of 130 Ω. It carries a current of 0.550 A. What is the energy stored in the magnetic field? At what rate is thermal energy developed in the inductor? Part A What is the energy stored in the magnetic field? Part B At what rate is thermal energy developed in the inductor?
1.    When measuring infrared area reflectivity, what is used as a reference material? a.      Gold b.     Steel c.      Silicon d.   &
1.    When measuring infrared area reflectivity, what is used as a reference material? a.      Gold b.     Steel c.      Silicon d.     Tungsten 2.    What is true about the light source for photoelectron spectroscopy? a.      Hit a pure metal with an accelerated electron, resulting in a single-energy X-ray. b.     The energy of the UV light represents almost constant energy regardless of the discharge gas. c.      The use of radiation accelerators allows the use of light from various energies. d.     Monochromator can increase light intensity. 3.    Which of the following statements is incorrect? a.    Initial...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT