Question

In: Operations Management

Question 2: The activities needed to develop a new software application are listed in the following...

Question 2: The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:

Activity Duration (weeks) Immediate Predecessor(s)
A 3 -
B 8 A
C 7 A
D 9 A
E 6 A
F 10 B, C
G 11 D, E
H 5 F, G
- - -

What is the duration of the project (in weeks)?

What is the earliest week you could start activity H?

What is the latest week you could start activity B?

What is the slack time for activity F?

What is the latest week you could finish activity D?

What would be the overall duration of the project if activity E were increased by 2 weeks (from 6 to 8 weeks)?

What would be the overall duration of the project if activity B were increased by 4 weeks (from 8 to 12 weeks)?

(Please list all the steps taken to solve this. Thanks in advance!)

Solutions

Expert Solution

The alternate paths in the network and their respective durations are listed below:

A-B-F-H, duration = 3+8+10+5 = 26

A-C-F-H, duration = 3+7+10+5 = 25

A-D-G-H, duration = 3+9+11+5 = 28

A-E-G-H, duration = 3+6+11+5 = 25

The longest path is A-D-G-H. Therefore, it is the critical path.

Duration of the project = 28 weeks

Activity H is critical. Therefore, its slack time is 0. The earliest it can start is 28-5 = week 23

Activity B is on a path whose duration is 26 weeks, which is 2 weeks less than the project duration. Therefore, its slack time is 2 weeks. The latest it can start is 3+2 = week 5


Related Solutions

Give an example of application of differential equation in software engineering.Explain with an example question.
Give an example of application of differential equation in software engineering.Explain with an example question.
examine the entrepreneurial activities that are needed for drawing up the strategies of a new business
examine the entrepreneurial activities that are needed for drawing up the strategies of a new business
A programmer plans to develop a new software system. In planning for the operating system that...
A programmer plans to develop a new software system. In planning for the operating system that he will? use, he needs to estimate the percentage of computers that use a new operating system. How many computers must be surveyed in order to be 90?% confident that his estimate is in error by no more than four percentage points? B) Assume that a recent survey suggests that about 91?% of computers use a new operating system
A programmer plans to develop a new software system. In planning for the operating system that...
A programmer plans to develop a new software system. In planning for the operating system that he will​ use, he needs to estimate the percentage of computers that use a new operating system. How many computers must be surveyed in order to be 95​% confident that his estimate is in error by no more than five percentage points question marks? Complete parts​ (a) through​ (c) below. Round to nearest integer. Assume that nothing is known about the percentage of computers...
A programmer plans to develop a new software system. In planning for the operating system that...
A programmer plans to develop a new software system. In planning for the operating system that he will​ use, he needs to estimate the percentage of computers that use a new operating system. How many computers must be surveyed in order to be 9595​% confident that his estimate is in error by no more than fivefive percentage points question mark s? Complete parts​ (a) through​ (c) below. ​a) Assume that nothing is known about the percentage of computers with new...
A programmer plans to develop a new software system. In planning for the operating system that...
A programmer plans to develop a new software system. In planning for the operating system that he will​ use, he needs to estimate the percentage of computers that use a new operating system. How many computers must be surveyed in order to be 99​% confident that his estimate is in error by no more than three percentage points question marks? ​a) Assume that nothing is known about the percentage of computers with new operating systems. n=___ ​b) Assume that a...
A programmer plans to develop a new software system. In planning for the operating system that...
A programmer plans to develop a new software system. In planning for the operating system that he will​ use, he needs to estimate the percentage of computers that use a new operating system. How many computers must be surveyed in order to be 95​% confident that his estimate is in error by no more than five percentage points question marks? Complete parts​ (a) through​ (c) below. ​a) Assume that nothing is known about the percentage of computers with new operating...
Situation: Your manager is leading a project to develop new software that is essential to the...
Situation: Your manager is leading a project to develop new software that is essential to the success of the midsized manufacturing firm where you work. The firm has decided to hire outside contractors to execute the project. One candidate firm boasts that its software development practices are at level 4 of CMMI. Another firm claims that all its software development practices are ISO 9001 compliant. Your manager has come to you and asked for your opinion on how much weight...
Discuss the importance of marketing activities for each of the segments listed in the previous question....
Discuss the importance of marketing activities for each of the segments listed in the previous question. Discuss and explain how important you think advertising is for each of the market segments. Provide specific examples. Discuss and explain how important you think personal sales is for each of the market segments. Provide specific examples. Discuss and explain how important you think sales promotions are for each of the market segments. Provide specific examples. Discuss and explain how important you think public...
Write all application functional specification for the following application, just the functional specification thanks. Develop a...
Write all application functional specification for the following application, just the functional specification thanks. Develop a shopping cart application (think of a simplified version of amazon.com). When the application begins, it shows a login window. Depending who logs in, a customer or the seller, the application performs different functions. Minimal Functional Specification: Here is a draft version of a minimal functional specification. Students have to adapt it, extend it, and make it their own: A customer logs in with a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT