In: Operations Management
Case Scenario: You are a manager the production process within ABC Inc. The facility consists of three different assembly lines (1, 2, 3) making two different products, X and Y. Assembly Line 2 is dedicated to the assembly of product X, and assembly line 3 is dedicated to product Y. Assembly Line 1 can assemble both the products. The production process begins with the procurement of raw materials from suppliers. Next, the raw materials are processed into six independent subassemblies, A–F, in separate work areas within the facility. Each product is then assembled from these subassemblies in one of the assembly lines. Product X involves the assembly of subassemblies A, B, C, and E. Product Y requires that subassemblies B, C, D, E, and F be assembled. Subsequent to assembly, each product is finished, customized (painted and other options added), packaged and shipped. Current trends indicate that 20% of product X and 50% of product Y are customized.
Following are the capacities of the work areas producing the subassemblies:
Subassembly Type |
Capacity (Units/Week) |
A |
2500 |
B |
2400 |
C |
2400 |
D |
2250 |
E |
3500 |
F |
1200 |
The annual demands for the products are as shown below:
Product |
Sub-assemblies required for one unit of product |
Annual Unit Sales |
X |
(2 of A); (1 of B, C, E) |
52,000 |
Y |
(1 of B, C, F); (2 of D, E) |
52,000 |
The capacities of the assembly lines and the finishing, packaging and customizing areas are as given below:
Assembly line 1 1200 units/week Finishing 2500 units/week
Assembly line 2 500 units/week Customizing 820 units/week
Assembly line 3 600 units/week Packaging 3000 units/week
Assumptions: (1) Assume 52 operating weeks/year.
(2) Plan production to just meet the demand (do not overproduce).
Answer the following questions. Show your calculations.
1. The key business problem in such situation is identification of the bottleneck resource. With the weekly demands of 1000 for each product X and Y, what is the current bottleneck resource?
2. Management must deal with changing demand and resource constraint, by analyzing alternative business scenarios. If the weekly demand for X and Y increased proportionately, identify the top three resources that are bottleneck candidates.
3. What does the above analysis tell you about the effect of demand changes in the product mix of a multiple product plant, on bottleneck shift? Justify your answer.
(1)
Demand | ||||
X | 1000 | |||
Y | 1000 | |||
Resources | Load | Capacity | Bottleneck? | Capacity - Load |
Assy 1 | 1100 | 1200 | No | 100 |
Assy 2 | 400 | 500 | No | 100 |
Assy 3 | 500 | 600 | No | 100 |
A | 2000 | 2500 | No | 500 |
B | 2000 | 2400 | No | 400 |
C | 2000 | 2400 | No | 400 |
D | 2000 | 2250 | No | 250 |
E | 3000 | 3500 | No | 500 |
F | 1000 | 1200 | No | 200 |
Finishing | 2000 | 2500 | No | 500 |
Customizing | 700 | 820 | No | 120 |
Packaging | 2000 | 3000 | No | 1000 |
Since there were no specific mix requirements of X and Y in the three assembly units, we have taken the loads strategically to avoid forming any bottleneck. So, under this condition, there is no real bottleneck up to an increase of 100 units per week.
But from the point of view of the minimum capacity, Assembly 2 is the next candidate for bottleneck because it has the least capacity.
2.
Since the (Capacity - Load) gap is least for the three assemblies, when we increase the demand of X and Y, the three assemblies will become bottlenecks step-by-step. After that 'Customization' will become bottlenecks. Following are such configurations.
3.
This tells us that by appropriately choosing the product mix, bottlenecks can be created/ eliminated/ shifted. The management can decide the process station bottlenecks if it has flexibility in production. The emergence of bottlenecks can be delayed if there is flexibility in the system (in this case, the Assembly 1). More the flexibility later is the appearance of the bottleneck in the system.