In: Accounting
PRACTICAL QUESTION
Tiger Construction Ltd signs a contract on 1 May 2018 to build a theme park. The construction is scheduled to commence on 1 July 2018 and the estimated date of completion is 30 June 2021. The total contract price is $5m and the cost of the park is initially estimated at $4.5m. The following data relates to the construction period:
For the year ended 30 June |
|||
2019 |
2020 |
2021 |
|
$ |
$ |
$ |
|
Costs to date |
1,700,000 |
3,000,000 |
4,800,000 |
Estimated costs to complete |
2,800,000 |
1,700,000 |
- |
Progress billings to date |
1,400,000 |
2,600,000 |
5,000,000 |
Cash received to date |
1,200,000 |
2,200,000 |
5,000,000 |
Assume that cost (an input measure) is used as the basis for assessing progress on the construction contract.
Required
Determine the percentage of completion for 2019, 2020 and 2021.
2019 |
2020 |
2021 |
|
$ |
$ |
$ |
|
Costs to date (A) |
|||
Estimated costs to complete (B) |
|||
Estimated total cost (A+B=C) |
|||
Percent of completion (POC=A/C) |
Calculate revenue and gross profit for 2019, 2020 and 2021.
2019 |
2020 |
2021 |
|||||
$ |
$ |
$ |
|||||
Contract Price |
|||||||
Contact Price x POC |
|||||||
LessRevenue recognised in previous years |
|||||||
= Revenue recognised for the year |
|||||||
Less Costs for the year |
|||||||
= Gross profit for the year |
|||||||
Using the percentage of completion method, provide the journal entries for 2019, 2020 and 2021.
2019 $m |
2020 $m |
2021 $m |
|||
(i) |
To record costs incurred: |
||||
(ii) |
To record billings to customers: |
||||
(iii) |
To record cash collections: |
||||
(iv) |
To record periodic income recognised: |
||||