Question

In: Finance

In 2008, a project requires an initial cost of -$250 and next year, in 2009, the...

In 2008, a project requires an initial cost of -$250 and next year, in 2009, the investor receives $570 and the year after that, in 2010, the cash flows from the investment is -$120. What is the total number of IRRs in this project?

1

0

2

3

What is the NPV of a project if IRR < discount rate (Assuming that the first cash flow is negative and all of the cash flows from the project are positive)?

< 0

> 0

= 0

None

Which of the following method must be preferred if the number changes in the signs of future cash flows within the project’s economic life is more than one?

IRR

Payback Period

Discounted Payback Period

NPV

Solutions

Expert Solution

Answer to 1st Question

We see that the cash flows change from negative to positive and then again negative from year 0,1 and 2 respectively. Therefore the cash flows change signs more than once through out its life. In cases where signs of future cash flows within the project's economic life is more than 1 then the IRR of the prohect is more than 1.

Answer to 2nd Question

If Internal Rate Return of the project is greater than the discount rate then the NPV of the project is poitive and greater than 0

If Internal Rate Return of the project is less than the discount rate then the NPV of the project is negative and less than 0.

Discount rate is the monimum required rate of return whereas IRR is the return of the project where NPV is 0.

If IRR = Discount Rate then NPV of the project is 0

Answer to 3rd Question

When the Cash flows of a project change sign more than once throughout the life of the project then IRR of the project will be more than 1 and similarly Payback and Discounted Payback period will be more than 1.

Therefore in such instances, NPV Descsion rule should be preffered over IRR, Payback and Discounted Payback


Related Solutions

A company is considering a 3-year project that requires an initial installed equipment cost of $9,000....
A company is considering a 3-year project that requires an initial installed equipment cost of $9,000. The project engineer has estimated that the operating cash flows will be $4,000 in year 1, $6,000 in year 2, and $8,000 in year 3. The new machine will also require a parts inventory of $2,000 at the beginning of the project (assume this inventory can be sold for cost at the end of the project). It is also estimated that the equipment can...
A company is considering a 3-year project that requires an initial installed equipment cost of $10,000....
A company is considering a 3-year project that requires an initial installed equipment cost of $10,000. The project engineer has estimated that the operating cash flows will be $5,000 in year 1, $6,000 in year 2, and $9,000 in year 3. The new machine will also require a parts inventory of $1,000 at the beginning of the project (assume this inventory can be sold for cost at the end of the project). It is also estimated that the equipment can...
A company is considering a 3-year project that requires an initial installed equipment cost of $15,000....
A company is considering a 3-year project that requires an initial installed equipment cost of $15,000. The project engineer has estimated that the operating cash flows will be $5,000 in year 1, $7,000 in year 2, and $9,000 in year 3. The new machine will also require a parts inventory of $3,000 at the beginning of the project (assume this inventory can be sold for cost at the end of the project). It is also estimated that the equipment can...
A company is considering a 3-year project that requires an initial installed equipment cost of $10,000....
A company is considering a 3-year project that requires an initial installed equipment cost of $10,000. The project engineer has estimated that the operating cash flows will be $4,000 in year 1, $6,000 in year 2, and $8,000 in year 3. The new machine will also require a parts inventory of $3,000 at the beginning of the project (assume this inventory can be sold for cost at the end of the project). It is also estimated that the equipment can...
Project A: This project requires an initial investment of $20,000,000 in equipment which will cost an...
Project A: This project requires an initial investment of $20,000,000 in equipment which will cost an additional $3,000,000 to install. The firm will use the attached MACRS depreciation schedule to expense this equipment. Once the equipment is installed, the company will need to increase raw goods inventory by $5,000,000, but it will also see an increase in accounts payable for $1,500,000. With this investment, the project will last 6 years at which time the market value for the equipment will...
An investment project requires an initial cost of $100. The project will provide $ 25 in...
An investment project requires an initial cost of $100. The project will provide $ 25 in the first year and $110 in the second year. What is the NPV of the project if the discount rate is 10%? $ 1.13 $ 13.64 $ 35 $ 3.35
A company is considering a 6-year project that requires an initial outlay of $23,000. The project...
A company is considering a 6-year project that requires an initial outlay of $23,000. The project engineer has estimated that the operating cash flows will be $4,000 in year 1, $6,000 in year 2, $7,000 in year 3, $7,000 in year 4, $7,000 in year 5, and $8,000 in year 6. At the end of the project, the equipment will be fully depreciated, classified as 5-year property under MACRS. The project engineer believes the equipment can be sold for $5,000...
A company is considering a 6-year project that requires an initial outlay of $30,000. The project...
A company is considering a 6-year project that requires an initial outlay of $30,000. The project engineer has estimated that the operating cash flows will be $3,000 in year 1, $6,000 in year 2, $7,000 in year 3, $7,000 in year 4, $7,000 in year 5, and $8,000 in year 6. At the end of the project, the equipment will be fully depreciated, classified as 5-year property under MACRS. The project engineer believes the equipment can be sold for $6,000...
Consider a project that has a 10% cost of capital that requires an initial investment of...
Consider a project that has a 10% cost of capital that requires an initial investment of $10,000. The year 1 net cash inflow is $2,450; the year 2 net cash inflow is $2,850; the year 3 net cash inflow is $3,350; the year 4 net cash inflow is $3,750; and the year 5 net cash inflow is $5,250. What is the project's discounted payback? NPV? AND IRR?
Dr. Chan is considering a four year project. The project requires an initial investment of $10,000,000...
Dr. Chan is considering a four year project. The project requires an initial investment of $10,000,000 to buy new equipment. The equipment will be depreciated straight line to zero over the project’s life. The company believes it can generate $5,000,000 in pretax revenues in year 1. Revenues will increase at 20% per year. Total pretax operating cost would be 40% of the pretax revenues. Net working capital will be 20% of the pretax revenue for the year. Net working capital...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT