Question

In: Finance

Rana Company has $300,000 to invest and wishes to evaluate the following three projects. Years X...

Rana Company has $300,000 to invest and wishes to evaluate the following three projects.

Years

X ($)

Y ($)

Z ($)

0

(150,000)

(150,000)

(100,000)

1

55,000

80,000

70,000

2

55,000

40,000

30,000

3

55,000

40,000

20,000

4

55,000

70,000

cost of capital

10%

10%

10%

Required:

Which project(s) would you recommend using:

  1. Payback Period (PP) in nominal and discounted values.
  2. Net Present Value (NPV)
  3. Profitability Index (PI)
  4. The internal rate of return (IRR) (hint: use 30%)

kindly note that i need the answer with full steps and clear and detials

Solutions

Expert Solution

Based on the given data, pls find below workings:

Based on the below workings, Project Z is having lower Payback (normal and discounted) period; However, since the payback method does not consider the cash flows post the payback period, the decision of investment should be chosen based on the other methods - IRR, NPV and NPV;

Based on all these three methods, Project Y is the top priority option for investment followed by Project X and then Project;

Considering the investment value of $ 300000, it is recommended to invest in Project Y and Project X to gain maximum benefits.

Computation of IRR: This can be computed using formula in Excel = IRR("range of cashflows", discounting factor%);

Computation of PI: Profitabliity index is computed as NPV / Initial Investment.

Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;

Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;

The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;

Computation of Pay Back Period: Here, the period is computed for each project, based on cumulative discounted cash flows: If the cumulative value is less than or equal to zero, the period is considered as 12 months (it means that the net cumulative cash flow has not yet paid back the initial investment); Once the value turns positive in a particular year, the period for such year is observed at a proportion of actual discounted cash flow to the cumulative CF; This gives the period less than 12 months in such year; Once this is computed, total of all the years is taken and divided by 12, to arrive at the Payback period in no.of years.


Related Solutions

Rana Company has $300,000 to invest and wishes to evaluate the following three projects. Years X...
Rana Company has $300,000 to invest and wishes to evaluate the following three projects. Years X ($) Y ($) Z ($) 0 (150,000) (150,000) (100,000) 1 55,000 80,000 70,000 2 55,000 40,000 30,000 3 55,000 40,000 20,000 4 55,000 70,000 cost of capital 10% 10% 10% Required: Which project(s) would you recommend using: Payback Period (PP) in nominal and discounted values. Net Present Value (NPV) Profitability Index (PI) The internal rate of return (IRR) (hint: use 30%)
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value...
Donahue Industries Inc. wishes to evaluate three capital investment projects by using the net present value method. Relevant data related to the projects are summarized as follows: Product Line Expansion Distribution Facilities Computer Network Amount to be invested $790,052 $535,506 $310,018 Annual net cash flows: Year 1 413,000 301,000 186,000 Year 2 384,000 271,000 128,000 Year 3 351,000 241,000 93,000 Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2...
You are ask to evaluate the following mutually exclusive projects, Project X which has an initial...
You are ask to evaluate the following mutually exclusive projects, Project X which has an initial cost of $5,060,000 and ten annual estimated net cash flows of $1,722,000 and Project Y which has an initial cost of $5,060,000 and five annual estimated cash flows of $2,079,000. Use two different standardized NPV methods to evaluate these projects at a cost of capital of 11 percent. (Please show all of your calculations).   Discuss the logic of each of these methods. Are they...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 5) Assuming the three projects X, Y & Z are...
consider the following three projects. All three have an initial investment of $300,000 Net Cash Inflows...
consider the following three projects. All three have an initial investment of $300,000 Net Cash Inflows Project L Project M Project N Year Annual Accumulated Annual Accumulated Annual Accumulated 1 $75,000 $75,000 $25,000 $25,000 $150,000 $150,000 2 75,000 150,000 75,000 100,000 150,000 300,000 3 75,000 225,000 200,000 300,000 4 75,000 300,000 250,000 550,000 5 75,000 375,000 350,000 900,000 6 75,000 450,000 7 75,000 525,000 8 75,000 600,000 Required 1. Determine the payback period of each project. Rank the projects from...
Investor X has 7,000 to spend on the following three projects. Use the AW method to...
Investor X has 7,000 to spend on the following three projects. Use the AW method to determine which of these independent investments are financially acceptable at 6% per year compounded monthly interest rate. Option Installed Cost Return per month A 4500 220 B 3000 200 C 2200 140 Lifelong period. Use CC=AW/i to get present worth See Below Answer. How do you get this answer? P5 PP-Month done by instrutor CP-Month done by instrutor Time Window - Month A $                  ...
Suppose a company has two mutually exclusive projects, both of which are three years in length....
Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $6,000 and has expected cash flows of $4,000 in year 1, $5,000 in year 2, and $5,000 in year 3. Project B has an initial outlay of $9,000 and has expected cash flows of $2,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 10% for projects at...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT