Question

In: Finance

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...

The most likely outcomes for a particular project are estimated as follows:

Unit price: $ 80

Variable cost: $ 60

Fixed cost: $ 440,000

Expected sales: 40,000 units per year

However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated straight-line over the project life to a final value of zero. The firm’s tax rate is 21% and the required rate of return is 14%.

(For all the requirements, a negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.)

b. What is project NPV in the worst-case scenario?

Solutions

Expert Solution

In the worst case scenario the unit price and expected sales will be 5% lower and variable cost and fixed cost will be 5% higher.

Annual depreciation = $1.1 million/10 years = $0.11 million per year

Then the cash flows will be:

Sales = 40,000 units * (1-0.05) * $80 unit price * (1-0.05)

= 38,000 units * $76

= $2,888,000

Variable cost = 38,000 units * $60 * (1+0.05) = $2,166,000

Fixed costs = $440,000*(1+0.05) = $462,000

Now operating cash flow = EBIT + Depreciation - Tax

a b c d e f g = c - d - e - f h I = g + f - h
Year Initial investment Sales Variable costs Fixed costs Depreciation EBIT Tax = 21% of EBIT Operating cash flow
0 - 1,100,000
                1          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                2          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                3          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                4          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                5          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                6          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                7          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                8          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
                9          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500
              10          2,888,000              2,166,000           462,000              110,000               150,000          31,500         228,500

Using the operating cash flow we can compute the NPV:

Year (t) Initial investment Operating cash flow 1+r PV = operating cash flow/(1+r)^t
0 - 1,100,000                        1.14 - 1,100,000.00
                1        228,500.00        200,438.60
                2        228,500.00        175,823.33
                3        228,500.00        154,230.99
                4        228,500.00        135,290.34
                5        228,500.00        118,675.74
                6        228,500.00        104,101.53
                7        228,500.00          91,317.13
                8        228,500.00          80,102.74
                9        228,500.00          70,265.56
              10        228,500.00          61,636.46
NPV         91,882.43

Thus NPV = $91,882.43 in the worst case scenario.


Related Solutions

The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 380,000 Expected sales: 37,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.7 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 440,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 80 Variable cost: $ 60 Fixed cost: $ 440,000 Expected sales: 40,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 5% higher or 5% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 340,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 410,000 Expected sales: 40,000 units per year Modern Artifacts can produce keepsakes that will be sold for $60 each. Nondepreciation fixed costs are $1,400 per year, and variable costs are $30 per unit. The initial investment of $5,000 will be depreciated straight-line over its useful life of 5 years to a final value of zero, and the...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 490,000 Expected sales: 48,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.3 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 420,000 Expected sales: 47,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.1 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 60 Variable cost: $ 40 Fixed cost: $ 250,000 Expected sales: 30,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.2 million, which will be depreciated...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50...
The most likely outcomes for a particular project are estimated as follows: Unit price: $ 50 Variable cost: $ 30 Fixed cost: $ 360,000 Expected sales: 35,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.6 million, which will be depreciated...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT