In: Accounting
Analyzing Manufacturing Cost Accounts
Fire Rock Company manufactures designer paddle boards in a wide variety of sizes and styles. The following incomplete ledger accounts refer to transactions that are summarized for June:
Materials | |||||
---|---|---|---|---|---|
June 1 | Balance | 35,800 | June 30 | Requisitions | (A) |
June 30 | Purchases | 143,900 |
Work in Process | |||||
---|---|---|---|---|---|
June 1 | Balance | (B) | June 30 | Completed jobs | (F) |
June 30 | Materials | (C) | |||
June 30 | Direct labor | (D) | |||
June 30 | Factory overhead applied | (E) |
Finished Goods | |||||
---|---|---|---|---|---|
June 1 | Balance | 0 | June 30 | Cost of goods sold | (G) |
June 30 | Completed jobs | (F) |
Wages Payable | |||||
---|---|---|---|---|---|
June 30 | Wages incurred | 123,800 | |||
Factory Overhead | |||||
---|---|---|---|---|---|
June 1 | Balance | 21,700 | June 30 | Factory overhead applied | (E) |
June 30 | Indirect labor | (H) | |||
June 30 | Indirect materials | 19,100 | |||
June 30 | Other overhead | 75,900 |
In addition, the following information is available:
a. Materials and direct labor were applied to six jobs in July:
Job No. | Style | Quantity | Direct Materials | Direct Labor | ||||||||
201 | T100 | 220 | $24,640 | $17,000 | ||||||||
202 | T200 | 390 | 36,730 | 25,000 | ||||||||
203 | T400 | 220 | 17,780 | 9,000 | ||||||||
204 | S200 | 300 | 43,800 | 29,000 | ||||||||
205 | T300 | 160 | 20,640 | 15,000 | ||||||||
206 | S100 | 150 | 9,450 | 4,000 | ||||||||
Total | 1,440 | $153,040 | $99,000 |
b. Factory overhead is applied to each job at a rate of 140% of direct labor cost.
c. The June 1 Work in Process balance consisted of two jobs, as follows:
Job No. | Style | Work in Process, June 1 | |||
201 | T100 | $6,500 | |||
202 | T200 | 15,200 | |||
Total | $21,700 |
d. Customer jobs completed and units sold in July were as follows:
Job No. | Style | Completed in July | Units Sold in July | |
201 | T100 | X | 176 | |
202 | T200 | X | 312 | |
203 | T400 | 0 | ||
204 | S200 | X | 252 | |
205 | T300 | X | 133 | |
206 | S100 | 0 |
1. Determine the missing amounts associated with each letter and complete the following table. If required, round amounts to the nearest dollar. If an answer is zero, enter in "0". Enter all amounts as positive numbers.
Job No. | Quantity | June 1 Work in Process |
Direct Materials |
Direct Labor |
Factory Overhead |
Total Cost | Unit Cost | Units Sold | Cost of Goods Sold | ||||||||
No. 201 | $ 6,500 | $ 24,640 | $ 17,000 | $ | $ | $ | $ | ||||||||||
No. 202 | 15,200 | 36,730 | 25,000 | ||||||||||||||
No. 203 | 17,780 | 9,000 | |||||||||||||||
No. 204 | 43,800 | 29,000 | |||||||||||||||
No. 205 | 20,640 | 15,000 | |||||||||||||||
No. 206 | 9,450 | 4,000 | |||||||||||||||
Total | $21,700 | 153,040 | 99,000 | $ | $ | $ |
a. Materials Requisitions $
b. Work in Process Beginning Balance $
c. Direct Materials $
d. Direct Labor $
e. Factory overhead applied $
f. Completed jobs $
g. Cost of goods sold $
h. Indirect labor $
2. Determine the June 30 balances for each of the inventory accounts and factory overhead. Use the minus sign to indicate any credit balances.
Materials: | $ |
Work in Process: | $ |
Finished Goods: | $ |
Factory Overhead: | $ |
1.
a. Materials Requisitions : $ 172,140
b. Work in Process beginning balance : $ 21,700
c. Direct Materials : $ 153,040
d. Direct Labor : $ 99,000.
e. Factory Overhead Applied : $ 138,600
f. Completed Jobs : $ 353,910
g. Cost of Goods Sold : $ 289,434
h. Indirect Labor : $ 24,800
Job No. | Quantity | June 1 Work in Process | Direct Materials | Direct Labor | Factory Overhead | Total Cost | Unit Cost | Units Sold | Cost of Goods Sold |
201 | 220 | $ 6,500 | $ 24,640 | $ 17,000 | $ 23,800 | $ 71,940 | $ 327 | 176 | $ 57,552 |
202 | 390 | 15,200 | 36,730 | 25,000 | 35,000 | 111,930 | 287 | 312 | 89,544 |
203 | 220 | 0 | 17,780 | 9,000 | 12,600 | 39,380 | 179 | 0 | 0 |
204 | 300 | 0 | 43,800 | 29,000 | 40,600 | 113,400 | 378 | 252 | 95,256 |
205 | 160 | 0 | 20,640 | 15,000 | 21,000 | 56,640 | 354 | 133 | 47,082 |
206 | 150 | 0 | 9,450 | 4,000 | 5,600 | 19,050 | 127 | 0 | 0 |
Totals | 1,440 | $ 21,700 | $ 153,040 | $ 99,000 | $ 138,600 | $ 412,340 | $ 289,434 |
2.
Materials | $ 7,560 |
Work in Process | 58,430 |
Finished Goods | 64,476 |
Factory Overhead | 2,900 |