In: Operations Management
The owner of a small social services management consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Adil, Barry, Camilla, and Diana -- to complete any of the four projects, as follows:
Project Hours |
||||
Consultant |
A |
B |
C |
D |
Adela |
18 |
22 |
16 |
17 |
Bijeesh |
13 |
14 |
22 |
16 |
Conrad |
21 |
11 |
19 |
17 |
Destiny |
15 |
12 |
19 |
20 |
**Please show excel steps so I can see if I was able to do this right** THANK YOU
What is the total number of hours required by the following arbitrary assignment? Adela→B; Bijeesh→A; Conrad→D; Destiny→C
What is the optimal assignment of consultants to projects? (Use the assignment method; SHOW YOUR WORK!)
For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
We tabulate the data as shown below:
The above table in the form of formulas is shown below for better understanding and reference:
We assign the consultants as given in the question:
As seen from above, we get the total time as shown in orange = 71 hours
We now find the optimal assignment using Excel Solver as shown below:
The Solver extract is shown below for better understanding and reference:
The optimal assignment is shown in the upper table.
The time taken is shown in orange = 58 hours
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.