Question

In: Finance

modern refurbishing inc. is considering a project that has the following cash flow data. What is...

modern refurbishing inc. is considering a project that has the following cash flow data. What is the project IRR? Note that a projects IRR can be less than the cost of capital (and even negative, In which case will it be rejected.

Year 0 1 2 3

CF -$900 $330 %315 $300 $270

Solutions

Expert Solution

Answer:

We will calculate IRR using interpolation method

Year CF PV at 12% Discounted Cash flows
0    -900.00 1                            -900.00
1     330.00 0.8929                              294.66
2     315.00 0.7972                              251.12
3     300.00 0.7118                              213.54
4     270.00 0.6355                              171.59
                               30.90
Year CF PV at 16% Discounted Cash flows
0    -900.00 1                            -900.00
1     330.00 0.8621                              284.49
2     315.00 0.7432                              234.11
3     300.00 0.6407                              192.21
4     270.00 0.5523                              149.12
                             -40.07

Now, IRR =Start rate+(NPV at start rate / NPV at start rate - NPV at end rate) X Difference between rate.

IRR = 12 + (30.90 / 30.90+40.07) * 4
IRR = 13.74%

Since the cost of capital is not given in the question, we could not comment whether the project should be accepted or rejected.
As per IRR rule, the project should be accepted if the IRR is greater than the cost of the capital.


Related Solutions

modern refurbishing inc. is considering a project that has the following cash flow data. What is...
modern refurbishing inc. is considering a project that has the following cash flow data. What is the project IRR? Note that a projects IRR can be less than the cost of capital (and even negative, In which case will it be rejected. Year 0 1 2 3 CF -$900 $330 %315 $300 $270
modern refurbishing inc. is considering a project that has the following cash flow data. What is...
modern refurbishing inc. is considering a project that has the following cash flow data. What is the project IRR? Note that a projects IRR can be less than the cost of capital (and even negative, In which case will it be rejected. Year 0 1 2 3 CF -$900 $330 %315 $300 $270 A. A. 13.68, b. 14.09 c. 14.24, d. 14.75, e/ 15.16
Redesign Inc. is considering a project that has the following cash flow data. (a) What is...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is the project's payback period? (b) What is the project's discounted payback period? Assume the cost of capital is 12%. Year 0 1 2 3 Cash flows -$500 $200 $200 $200
Susmel Inc. is considering a project that has the following cash flow data. What is the...
Susmel Inc. is considering a project that has the following cash flow data. What is the project's payback? No original investment given Year 0 1 2 3 Cash flows -$500 $150 $200 $300 Group of answer choices 1.90 years 2.63 years 2.50 years 1.93 years
Nichols Inc. is considering a project that has the following cash flow data. What is the...
Nichols Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected. Year 0 1 2 3 4 5 Cash flows −$1,250 $325 $325 $325 $325 $325 a. 11.47% b. 10.40% c. 9.43% d. 10.92% e. 9.91% Westwood Painting Co. is considering a project that has the following cash flow and cost...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is the project's discounted payback? WACC:  15.00% Year                            0                1                2                3                4     Cash flows              -$750         $525          $485          $445          $405 Hint: Discounted Payback period: The number of years required to recover a project’s cost. Cumulative cash flow computation takes into account the time value of money by using discounted cash flows. Group of answer choices 1.68 years 1.99 years 1.80 years 2.22 years 2.44 years
XYZ Inc. is considering a new project that has the following cash flow data. What is...
XYZ Inc. is considering a new project that has the following cash flow data. What is the project's IRR? Year 0 1 2 3 4 5 Cash Flows -1043 340 340 340 340 340
Harry's Inc. is considering a project that has the following cash flow and WACC data. What...
Harry's Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected. WACC: 13.25% Year 0 1 2 3 4 5 Cash flows -$1,000 $300 $300 $300 $300 $300
Harry's Inc. is considering a project that has the following cash flow and WACC data. What...
Harry's Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected.
 WACC: 7.75% Year 0 1 2 3 4 5 Cash flows -$1,000 $300 $300 $300 $300 $300 a. 209.86 b. 248.95 c. 205.75 d. 176.94 e. 232.49
Harry's Inc. is considering a project that has the following cash flow and WACC data. What...
Harry's Inc. is considering a project that has the following cash flow and WACC data. What is the project's NPV? WACC: 10.75% Year 0 1 2 3 4 5 Cash flows −$1,000 $310 $310 $310 $310 $310
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT