Question

In: Mechanical Engineering

A manufacturing operation requires 50 fc on the workplane in a 100 ft x 150 ft...

A manufacturing operation requires 50 fc on the workplane in a 100 ft x 150 ft facility. The walls and ceilings are painted white. The work plane is 25 feet below the lights.

1. Calculate how many high-bay 400-W metal halide fixtures are required

2. Calculate how many 6-lamp T8 HBF fixtures are required.

Solutions

Expert Solution

Given data,

Both walls and ceilings are white ,

Rc = reflectivity of ceiling = 100%
Rw = reflectivity of walls = 100%

Ew = 50 fc ,

H = height = 25 ft,
W = width = 150 ft ,
L = length = 100 ft ,

Area of work plane (A) = W*L = 15000 ft2 ,

Room-Cavity Ratio (RCR)

RCR = 5H*(W + L) / (W*L)

        = 5*25*(150 + 100) / (150*100)

        = 2.08 ~ 2

1. Number of high-bay 400-W metal halide (N)

From CU table,

Coefficient of Utilization (CU) for 400-W metal halide = 0.80
Lumens Per Fixture (LPF) for 400-W metal halide = 23,500 lm

Now,

N = (Ew * A) / (CU * LPF)

   = (50 * (100 * 150)) / (.80 x 23,500)

   = 39.89 ~ 40 lights

2. Number of 6-lamp T8 HBF (N)

Coefficient of Utilization (CU) for 6-lamp T8 HBF = 0.82
Lumens Per Fixture (LPF) for 6-lamp T8 HBF = 20,500 lm

N = (Ew * A) / (CU * LPF)

   = (50 * (100 * 150)) / (.82 x 23,500)

   = 44.61 ~ 45 lights


Related Solutions

Problem 2 : If the slab is 25 ft wide x 50 ft long x 18...
Problem 2 : If the slab is 25 ft wide x 50 ft long x 18 inches deep with the total steel reinforcement of 15,000 ft of #5 bar. Find the quantity of concrete required (in cubic yards). The capacity of concrete truck is 9 cubic yards. Assume waste factor as 10%. Density of steel is 490 lbs/cubic feet. Problem 3 : If the slab is 75 ft wide x 100 ft long x 9 inches deep with the total...
Linear regression question If the range of the x-values are from x=100 to x=150, why might...
Linear regression question If the range of the x-values are from x=100 to x=150, why might we be reluctant to use our data to perform a hypothesis test on β0?
A filled water bed has the dimensions 8.0 ft x 7.0 ft x 0.75 ft. Determine...
A filled water bed has the dimensions 8.0 ft x 7.0 ft x 0.75 ft. Determine the mass of water, in kilograms, needed to fill the bed. Density of water = 1.00 g/cm^3.
A pizza baker uses 100 slices of pepperoni, 50 slices of mushrooms and 150 slices of...
A pizza baker uses 100 slices of pepperoni, 50 slices of mushrooms and 150 slices of peppers for each pizza pie. After baking, he divides the pies in 10 slices. What is the probability that in one slice of pizza… There are at most 8 slices of pepperoni: 0.6672     b) 0.6472                c) 0.2202                   d) 0.3328 No mushrooms at all: 0.0067     b) 0.0498                 c) 0                              d) 0.0302 Less than 13 pepper slices: 0              b)...
1- A carpenter purchased 50 ft of redwood and 70 ft of pine for a total...
1- A carpenter purchased 50 ft of redwood and 70 ft of pine for a total cost of $259. A second purchase, at the same prices, included 80 ft of redwood and 50 ft of pine for a total cost of $340. Find the cost per foot of redwood and of pine. 2- An investment club placed $27,000 into two simple interest accounts. On one account, the annual simple interest rate is 6.5%. On the other, the annual simple interest...
Design an isolated footing with one side limited to 7 ft for the following: 1 ft x 1 ft edge column, axial loads PD = 130 kip and PL = 155 kip, fc’ = 3,000 psi, fy = 60,000 psi, qa = 4 ksf
Design an isolated footing with one side limited to 7 ft for the following: 1 ft x 1 ft edge column, axial loads PD = 130 kip and PL = 155 kip, fc’ = 3,000 psi, fy = 60,000 psi, qa = 4 ksf, and a distance from top of backfill to bottom of footing is 4 ft. Assume the soil density is 100 pcf. For the column, fc’ = 5,000 psi. Sketch your design.
If the slab is 21 ft wide x 36 ft long x 15 inches deep with...
If the slab is 21 ft wide x 36 ft long x 15 inches deep with the total steel reinforcement of 20,000 ft of #5 bar. Find the quantity of concrete required (in cubic yards). The capacity of concrete truck is 9 cubic yards. Assume waste factor as 10%. Density of steel is 490 lbs/cubic feet. (a) Calculate Slab Volume: (b)Calculate Steel Volume and Weight: (c) Calculate concrete Volume:
explain production process, manufacturing operation and service operation.
explain production process, manufacturing operation and service operation.
Problem 2: A 3 ft x 5 ft (B x L) rectangular footing is shown in...
Problem 2: A 3 ft x 5 ft (B x L) rectangular footing is shown in following figure. Using generalized bearing equation (with shape, depth and inclination factors), determine the allowable (safe) load that the foundation carry. Given: gamma = 115 lb/ft3 , c’= 1100 lb/ft2 , phi’ = 35°, Df =3.5 ft, Ground water table is located at 5 ft below ground level. Assume factor of safety = 3. Assume gammasat = 127.4 lb/ft
Murphy was consuming 100 units of X and 50 units of Y . Theprice of...
Murphy was consuming 100 units of X and 50 units of Y . The price of X rose from $2 to $3. The price of Y remained at $4.(a) How much would Murphyís income have to rise so that he can still exactly a§ord 100 units of X and 50 units of Y ? Assume that Murphy spends all of his income on X and Y .(b) Now say that Murphyís income falls to $300. If the price of Y...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT