In: Accounting
Problem 9-21 Multiple Products, Materials, and Processes [LO9-4, LO9-5]
Mickley Corporation produces two products, Alpha6s and Zeta7s, which pass through two operations, Sintering and Finishing. Each of the products uses two raw materials—X442 and Y661. The company uses a standard cost system, with the following standards for each product (on a per unit basis):
Raw Material | Standard Labor Time | ||||
Product | X442 | Y661 | Sintering | Finishing | |
Alpha6 | 2.0 kilos | 1.5 liters | 0.10 hours | 0.80 hours | |
Zeta7 | 3.0 kilos | 2.5 liters | 0.45 hours | 0.90 hours | |
Information relating to materials purchased and materials used in production during May follows:
Material | Purchases | Purchase Cost | Standard Price |
Used in Production |
|||
X442 | 14,800 | kilos | $66,600 | $4.30 | per kilo | 9,300 | kilos |
Y661 | 15,800 | liters | $23,700 | $1.60 | per liter | 13,800 | liters |
The following additional information is available:
The standard labor rate is $22.00 per hour in Sintering and $21.00 per hour in Finishing.
During May, 1,220 direct labor-hours were worked in Sintering at a total labor cost of $28,060, and 2,930 direct labor-hours were worked in Finishing at a total labor cost of $67,390.
Production during May was 2,300 Alpha6s and 1,600 Zeta7s.
Required:
1. Complete the standard cost card for each product, showing the standard cost of direct materials and direct labor.
2. Compute the materials price and quantity variances for each material.
3. Compute the labor rate and efficiency variances for each operation.
SOLUTION:
1. standard cost card for each product, showing the standard cost of direct materials and direct labor.
Standard
quantity or hours |
Standard
price or rate |
Standard cost | |
Alpha6: | |||
Direct materials-X442 | 2 Kilos | 4.3 Per kilo | 8.6 |
Direct materials-Y661 | 1.5 Liters | 1.6 Per liter | 2.4 |
Direct labor-Sintering | 0.1 Hours | 22 Per hour | 2.2 |
Direct labor-Finishing | 0.8 Hours | 21 Per hour | 16.8 |
Total | 30 | ||
Zeta7: | |||
Direct materials-X442 | 3 Kilos | 4.3 Per kilo | 12.9 |
Direct materials-Y661 | 2.5 Liters | 1.6 Per liter | 4 |
Direct labor-Sintering | 0.45 Hours | 22 Per hour | 9.9 |
Direct labor-Finishing | 0.9 Hours | 21 Per hour | 18.9 |
Total | 45.7 |
2. Materials price and quantity variances for each material:
Material X442: | |||||||
Material price variance=Actual material purchased*(Standard rate for material-Actual rate for material) | |||||||
Actual material purchased=14800 Kilos | |||||||
Standard rate=$ 4.3 per kilo | |||||||
Actual rate=66600/14800=$4.5 per kilo | |||||||
Material price variance=14800*(4.3-4.5)=2960 U | |||||||
(Actual rate is more than the standard rate.Hence, variance is unfavorable) |
Material quantity variance=Standard rate for materials*(Standard materials required-Actual material used) | ||||||
Standard rate=$ 4.3 per kilo | ||||||
Standard materials required=Actual units produced*Material required per unit=(2300*2)+(1600*3)=9400 kilos | ||||||
Actual material used=9300 kilos | ||||||
Material quantity variance=4.3*(9400-9300)=430 F | ||||||
(Actual material used is less than the standard material required.Hence, variance is favorable) |
Material Y661: | |||||||
Material price variance=Actual material purchased*(Standard rate for material-Actual rate for material) | |||||||
Actual material purchased=15800 liters | |||||||
Standard rate=$ 1.6 per liter | |||||||
Actual rate=23700/15800=$1.5 per liter | |||||||
Material price variance=15800*(1.6-1.5)=1580 F | |||||||
(Actual rate is less than the standard rate.Hence, variance is favorable) |
Material quantity variance=Standard rate for materials*(Standard materials required-Actual material used) | ||||||
Standard rate=$ 1.6 per liter | ||||||
Standard materials required=Actual units produced*Material required per unit=(2300*1.5)+(1600*2.5)=7450 liters | ||||||
Actual material used=13800 liters | ||||||
Material quantity variance=1.6*(7450-13800)=10160 U | ||||||
(Actual material used is more than the standard material required.Hence, variance is unfavorable) |
3. Labor rate and efficiency variances for each operation:
Sintering: | |||||||
Labor rate variance=Actual hours worked*(Statndard labor rate-Actual labor rate) | |||||||
Actual hours worked=1220 hours | |||||||
Standard labor rate=$22 per hour | |||||||
Actual labor rate=Actual direct labor cost/Actual hours=28060/1220=$23 per hour | |||||||
Labor rate variance=1220*(22-23)=1220 U | |||||||
(Actual labor rate is more than standard labor rate.Hence variance is unfavorable) |
Labor efficiency variance=Standard labor rate*(Standard labor hours required-Actual labor hours worked) | |||||
Standard labor rate=$22 per hour | |||||
Standard labor hours required=Actual units produced*Labor hours required per unit=(2300*0.10)+(1600*0.45)=950 hours | |||||
Actual hours worked=1220 hours | |||||
Labor efficiency variance=22*(950-1220)=5940 U | |||||
(Actual hours worked is more than the standard hours required.Hence, variance is unfavorable) |
Finishing: | |||||||
Labor rate variance=Actual hours worked*(Statndard labor rate-Actual labor rate) | |||||||
Actual hours worked=2930 hours | |||||||
Standard labor rate=$21 per hour | |||||||
Actual labor rate=Actual direct labor cost/Actual hours=67390/2930=$23 per hour | |||||||
Labor rate variance=2930*(21-23)=5860 U | |||||||
(Actual labor rate is more than standard labor rate.Hence variance is unfavorable) |
Labor efficiency variance=Standard labor rate*(Standard labor hours required-Actual labor hours worked) | |||||
Standard labor rate=$21 per hour | |||||
Standard labor hours required=Actual units produced*Labor hours required per unit=(2300*0.80)+(1600*0.90)=3280 hours | |||||
Actual hours worked=2930 hours | |||||
Labor efficiency variance=21*(3280-2930)=7350 F | |||||
(Actual hours worked is less than the standard hours required.Hence, variance is favorable) |