In: Accounting
Exercise 7-13 Computing ABC Product Costs [LO7-3, LO7-4]
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
| Direct Labor-Hours per Unit  | 
Annual Production  | 
||
| Hubs | 0.60 | 19,000 | units | 
| Sprockets | 0.20 | 52,000 | units | 
Additional information about the company follows:
Hubs require $28 in direct materials per unit, and Sprockets require $12.
The direct labor wage rate is $19 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
| Estimated | Activity | ||||
| Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
| Machine setups (number of setups) | $ | 19,125 | 85 | 68 | 153 | 
| Special processing (machine-hours) | $ | 168,000 | 4,800 | 0 | 4,800 | 
| General factory (organization-sustaining) | $ | 136,200 | NA | NA | NA | 
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Requirement 1
| Activity Cost Pool | Activity rate (A/B) | |
| Machine setup | $ 125.00 | Per Setup | 
| Specil processing | $ 35.00 | Per machine hour | 
Working
| Calculation of Activity rates | |||||
| Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
| Machine setup | Number of Setup | $ 19,125.00 | 153 | $ 125.00 | Per Setup | 
| Special processing | Number of machine hour | $ 168,000.00 | 4800 | $ 35.00 | Per machine hour | 
.Requirement 2
| ABC Costing | ||
| Hubs | Sprockets | |
| Cost per Unit | $ 48.80 | $ 15.96 | 
Working
| Cost assigned to Hubs | |||
| Activity name | Activity Rates | Activity | ABC Cost | 
| (A) | (B) | (A x B) | |
| Machine setup | $ 125.00 | 85 | $ 10,625.00 | 
| Special processing | $ 35.00 | 4800 | $ 168,000.00 | 
| Total Overheads assigned | $ 178,625.00 | ||
.
| Cost assigned to Sprockets | |||
| Activity name | Activity Rates | Activity | ABC Cost | 
| (A) | (B) | (A x B) | |
| Machine setup | $ 125.00 | 68 | $ 8,500.00 | 
| Special processing | $ 35.00 | 0 | $ - | 
| Total Overheads assigned | $ 8,500.00 | ||
.
| ABC Costing | ||
| Hubs | Sprockets | |
| Direct material | $ 532,000.00 | $ 624,000.00 | 
| Direct labor | $ 216,600.00* | $ 197,600.00 | 
| Overheads | $ 178,625.00 | $ 8,500.00 | 
| Total Cost per unit | $ 927,225.00 | $ 830,100.00 | 
| Total Units | 19000 | $ 52,000.00 | 
| Cost per Unit | $ 48.80 | $ 15.96 | 
*19000 x .6 x $19