Question

In: Accounting

Firm A uses a process-costing system. For September 2020, the company had the following activities: Beginning...

Firm A uses a process-costing system. For September 2020, the company had the following activities:

Beginning work-in-process inventory 7,000 units
      Units placed in production, current 23,000 units
      Good units completed   25,000 units
      Ending work-in-process inventory 2,000 units
      Direct material costs, beginning $3,000
      Conversion costs, beginning $2,000
      Direct material costs, current $30,000
      Conversion costs, current    $10,000

Direct materials are placed into production at the beginning of the process. Beginning WIP is 100% complete as to direct materials and 30% complete as to conversion. All spoilage is detected at the end of the process. Normally, spoiled units are 10% of good units completed. Ending WIP is 60% completed as to conversion and 100% complete as to direct materials. The company decides to use the first-in, first-out (FIFO) method.

(26-1) Compute the physical units of normal spoilage and started and completed during current period. Then compute equivalent units for direct materials and conversion costs. (12 points)

(26-2) Summarize costs to account for and calculate cost per equivalent-unit for direct materials and conversion costs (Round cost per equivalent-unit calculations to the nearest hundredth). (4 points)

(26-3) Assign total costs (7 points)

(26-4) Calculate cost per good unit completed and normal spoilage rate. (4 points)

(26-5) Please briefly describe how does the job-costing system account for spoilage. (3 points)

(26-6) Please briefly explain why do we split completed units into completed units from beginning WIP and completed units from started and completed in current period under FIFO? (3 points)

Solutions

Expert Solution

Solution:

1

Started and Completed = Completed Good Units - Begining WIP = 25000 - 7000 = 18000

Normal Spoilage = 25000*10% = 2500 units

Abnormal Spoilage = Total Units - (Completed Units+Ending WIP+Normal Spoilage) = 500 units

2.

3.

4.

Cost per good units = 41112/25000 = $1.64

Normal Spoilage Rate = 4183/2500 = $1.67

PS: Dear student, kindly split up questions having multiple requirements. You can post 4 requirements per post. The first four is done for you. For any clarifications kindly use the comment box


Related Solutions

Luker Corporation uses a process costing system. The company had $172,500 of beginning Finished Goods Inventory...
Luker Corporation uses a process costing system. The company had $172,500 of beginning Finished Goods Inventory on October 1. It transferred in $849,000 of units completed during the period. The ending Finished Goods Inventory balance on October 31 was $170,200. The entry to account for the cost of goods sold in October is: Multiple Choice Debit Cost of Goods Sold $849,000; credit Finished Goods Inventory $849,000. Debit Cost of Goods Sold $851,300; credit Work in Process Inventory $851,300. Debit Finished...
The Poolside Company uses a FIFO process costing system. The following data are available: Beginning inventory...
The Poolside Company uses a FIFO process costing system. The following data are available: Beginning inventory 1,000 units (100% complete as to materials and 50% complete as to labor and overhead); Units started in production 19,000; Units finished during the period 16,000; Units in process at the end of the period (100% complete as to materials and 25% complete as to labor and overhead) 4,000; Costs in beginning inventory were materials of $1,500 and Labor and overhead costs $1,000; Cost...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria adopted the following standards: Inputs Total Direct materials 3 kg @ $2.50 per kg $7.50 Direct labour 5 hrs @ $7.50 per hr 37.50 Factory overhead: Variable $3.00 per direct labour hour 15.00 Fixed $4.00 per direct labour hour 20.00 Standard cost per unit $80.00 Alexandria’s July 2019 budget was based on the denominator volume of 40,000 direct labour hours. Alexandria’s actual July production...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria...
Alexandria Company uses a standard costing system. At the beginning of the 2020 financial year Alexandria adopted the following standards: Inputs Total Direct materials 3 kg @ $2.50 per kg $7.50 Direct labour 5 hrs @ $7.50 per hr 37.50 Factory overhead: Variable $3.00 per direct labour hour 15.00 Fixed $4.00 per direct labour hour 20.00 Standard cost per unit $80.00 Alexandria’s July 2019 budget was based on the denominator volume of 40,000 direct labour hours. Alexandria’s actual July production...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 20,000 Units finished during the period 16,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,000 Cost of materials used $ 35,200 Labor and overhead costs $ 37,400 Cost per equivalent unit of materials is: Multiple Choice $2.20. $2.07. $1.85. $1.76.
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 21,600 Units finished during the period 16,700 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 4,900 Cost of materials used $ 44,720 Labor and overhead costs $ 46,865 Total cost of the 16,700 units finished is: (Round intermediate calculations to two decimal places and round your final...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory...
The Lakeside Company uses a weighted-average process costing system. The following data are available: Beginning inventory -0- Units started in production 22,200 Units finished during the period 17,000 Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) 5,200 Cost of materials used $ 48,530 Labor and overhead costs $ 50,600 Total cost of the 17,000 units finished is: Multiple Choice $90,604. $99,164. $84,168. $88,534.
Thing Co. uses a job order costing system. At the beginning of July, the company had...
Thing Co. uses a job order costing system. At the beginning of July, the company had the following job in progress: Job 70 $16539 During July, Thing Co. incurred the following job related costs: Direct Materials Direct Labour Job 70 $2740 $1163 Job 80 12316 16294 Job 90 8248 7908 Manufacturing overhead is applied at a rate of $3.79 per $1 of direct labour cost. Jobs 70 and 90 were moved to finished goods during the month, but neither was...
ABC Company uses a job order costing system and had three jobs in process at the...
ABC Company uses a job order costing system and had three jobs in process at the beginning of the month. The beginning balance in the WIP account was $145,400, made up of $42,400, $65,100, and $37,900 as shown on the cost sheets for Jobs 921, 922, and 923 respectively. During the month, ABC added the following materials and labor costs to each job. Inventory Materials used for Month Labor Dollars used for Month Job 921 12,200 30,000 Job 922 13,400...
Williams uses a weighted-average process-costing system. All materials are added at the beginning of the process;...
Williams uses a weighted-average process-costing system. All materials are added at the beginning of the process; conversion costs are incurred evenly throughout production. The company finsihed 150,000 units during the period and has 80,000 units in progress at year-end, the latter at the 40% stage of completion. Total material costs amounted to $1,350,000; coversion costs were $1,600,000. The cost of the ending work-in process is?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT