The Rolling Department of Keystone Steel Company had 400 tons in beginning work in process inventory...

The Rolling Department of Keystone Steel Company had 400 tons in beginning work in process inventory (20% complete). During the period, 7,900 tons were completed. The ending work in process inventory was 1,000 tons (30% complete). What are the total equivalent units for direct materials if materials are added at the beginning of the process?

Solutions

Expert Solution

-Equivalent units for direct material is provided using BOTH -FIFO and Weighted average method below:

>As per FIFO = 8500 units

EUP - FIFO Method Units % Material EUP Materials
Units of ENDING WIP                                    1,000 100.0%                      1,000
Units STARTED & COMPLETED                                    7,500 100%                      7,500
Units of beginning WIP                                       400 0.00%                             -  
Equivalent Units of Production                      8,500

>As per Weighted average method = 8900 units

EUP - Weighted Average Method Units % Material EUP Materials
Units TRANSFERRED 7,900 100% 7,900
Units of ENDING WIP 1,000 100% 1,000
Equivalent Units of Production 8,900

Related Solutions

The Rolling Department of Kraus Steel Company had 5,300 tons in beginning work in process inventory...
The Rolling Department of Kraus Steel Company had 5,300 tons in beginning work in process inventory (30% complete) on October 1. During October, 87,500 tons were completed. The ending work in process inventory on October 31 was 4,400 tons (60% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? The total factory overhead for Bardot Marine Company is budgeted for the year at $1,296,900, divided into four...
The Rolling Department of Oak Ridge Steel Company had 5,100 tons in beginning work in process...
The Rolling Department of Oak Ridge Steel Company had 5,100 tons in beginning work in process inventory (90% complete) on July 1. During July, 85,400 tons were completed. The ending work in process inventory on July 31 was 4,300 tons (40% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Campbell Company had 400 units of product in work in process inventory at the beginning of...
Campbell Company had 400 units of product in work in process inventory at the beginning of the period. It started 1,300 units during the period and transferred 1,100 units to finished goods inventory. The ending work in process inventory was estimated to be 60 percent complete. Cost data for the period follow: Product Costs Beginning balance $ 37,560 Added during period 58,800 Total $ 96,360 Required Calculate the number of equivalent units of production. Calculate the product cost per equivalent...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel...
Process Cost Journal Entries The cost of materials transferred into the Rolling Department of Keystone Steel Company is $519,300 from the Casting Department. The conversion cost for the period in the Rolling Department is $112,500 ($67,700 factory overhead applied and $44,800 direct labor). The total cost transferred to Finished Goods for the period was $621,600. The Rolling Department had a beginning inventory of $22,400. a1. Journalize the cost of transferred-in materials. Accounts Payable Cash Factory Overhead-Casting Factory Overhead-Rolling Finished Goods...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 8,100 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 8,100 tons in beginning work in process inventory (50% complete) on October 1. During October, 50,800 tons were completed. The ending work in process inventory on October 31 was 2,500 tons (30% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process?
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 5,747 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 5,747 tons in beginning work in process inventory (60% complete) on October 1. During October, 82,100 tons were completed. The ending work in process inventory on October 31 was 4,105 tons (30% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. The Rolling Department of Kraus Steel Company had 5,300 tons in beginning work in process inventory (30% complete) on...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 8,684 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 8,684 tons in beginning work in process inventory (50% complete) on October 1. During October, 66,800 tons were completed. The ending work in process inventory on October 31 was 6,012 tons (80% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 8,503 tons in...
Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 8,503 tons in beginning work in process inventory (90% complete) on October 1. During October, 77,300 tons were completed. The ending work in process inventory on October 31 was 6,184 tons (60% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units Feedback Are you determining the equivalent units of materials added or of conversion of materials? When would materials...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 5,200 tons in...
Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 5,200 tons in beginning work in process inventory (30% complete) on October 1. During October, 86,600 tons were completed. The ending work in process inventory on October 31 was 4,300 tons (40% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company...
equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 6,125 tons in...
equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company had 6,125 tons in beginning work in process inventory (50% complete) on October 1. During October, 87,500 tons were completed. The ending work in process inventory on October 31 was 4,375 tons (90% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit.