In: Accounting
Use the following data to find the direct labor rate variance if the company produced 6,400 units of product during the period.
| Standard: | |||
|
Direct labor (3.3 hrs. per unit @ $10/hr.) |
$ | 33.00 | per unit |
| Actual cost incurred: | |||
|
Direct labor (22,920 hrs. @ $10.5/hr.) |
$ | 240,660 |
| WORKING NOTES: | |||||||||||
| Actual output = | 6400 | Units | |||||||||
| Standard Cost Per unit | Standard Cost for Actual Production | ||||||||||
| Standard Time | Std. Rate | Total Cost | Standard Time | Std. Rate | Total Std. Cost | Actual Time | Act. Rate | Actual Cost | |||
| 3.3 | $ 10.00 | $ 33 | 21120 | $ 10.00 | $ 2,11,200 | 22920 | $ 10.50 | $ 2,40,660 | |||
| Hrs | Per Hours | Hrs (6400 X 3.3) | Per Hours | Hrs | Per Hours | ||||||
| SOLUTION : 1 | |||||||||||
| Labour Total Cost Variance = Standard Cost of Labour - Actual Cost of Labour | |||||||||||
| Labour Cost Variance = | $ 2,11,200.00 | '-' | $ 2,40,660.00 | ||||||||
| Labour Cost Variance = | $ 29,460.00 | (Unfavorable) | |||||||||
| SOLUTION : 2 | |||||||||||
| Labour Rate Variance = (Actual Rate - Standard Rate) X Actual Hours | |||||||||||
| Labour Rate Variance = ( | $ 10.50 | '-' | $ 10.00 | ) X | 22,920 | ||||||
| Labour Rate Variance = | $ 0.50 | X | 22,920 | ||||||||
| Labour Rate Variance = | 11460 | (Unfavorable) | |||||||||
| SOLUTION : 3 | |||||||||||
| Labour Efficiency Variance = (Actual Hours - Standard Hours ) X Standard Rate | |||||||||||
| Labour Efficiency Variance = ( | 22,920.00 | '-' | 21,120.00 | ) X | $ 10.00 | ||||||
| Labour Efficiency Variance = | $ 1,800.00 | X | $ 10.00 | ||||||||
| Labour Efficiency Variance = | 18000 | (Unfavorable) | |||||||||