In: Finance
Problem set#4 Please find thefollowing information.
Scenario |
Probability (p) |
NPV (Million USD) |
Boom |
0.20 |
300 |
Average |
0.50 |
150 |
Bust |
0.30 |
-100 |
Solution :
A. The expected NPV from the investment project is = $ 105 million
Thus the expected NPV from the investment project will be closest to = $ 100 million
The solution is Option a = $ 100 million
B. The expected variance, σ2 of the NPV is = $ 21,225 Million.
Thus the expected variance, σ2 of the NPV will be closest to option c = $ 21,000 Million.
The solution is Option c = $ 21,000 million
C.The expected Standard deviation, σ of the NPV is = $ 145.6880 million
The expected Standard deviation, σ of the NPV will be closest to Option b. $ 150 million
The solution is Option b = $ 150 million
Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.