In: Finance
Is the following solution for the following question correct or not ? and if it's wrong where is the mistake and how to correct it?
Imagine that you own (250,000$) and you want to invest it in your dream plan. You have to consider two different alternatives. For each alternative, estimate the initial cost and annual cash flow details (operation and maintenance costs, raw material, salaries, overheads…etc.). Then compare these alternatives based on ROR criteria.
Note: you don’t need to consume the 250,000$, any cheaper investments are fine. Any larger investment is allowable under loan consideration or suitable explanation.
Since I am a mechanical Engineer, I decided to choose establishment of a Typical Automobile maintenance center:
The project life considered to be 10 years
# |
Type of expense |
Amount |
1 |
Fixed Assets cost |
100,000$ |
2 |
Premises rent |
20,000$ |
3 |
Operation cost |
15,285$ |
4 |
Maintenance for equipment cost |
3,500$ |
5 |
Salaries |
68,571$ |
6 |
Administration cost (Tax, Registration, …etc) |
10,000$ |
7 |
Overhead |
7,000$ |
100,000$ will be the initial cost payed once at the beginning of the project (year 0)
The running costs will be 124,356$ paid annually along the project life cycle with an annual increase of 2%
The expected revenue for the project is 170,340$ and expected to increase by 3% annually since the automobiles will need more repairs when it becomes older
The salvage value for the project will be 20,000$
Year |
Type of cost |
Cost |
Revenue |
Salvage |
Net |
PV Factor @ |
PV @ |
PV Factor |
PV |
PV Factor |
PV @ |
0 |
Establishment cost |
-100000 |
0 |
-100,000 |
- |
-100000 |
-100000 |
-100000 |
|||
1 |
Running cost |
-124,356 |
170,340 |
45,984 |
0.8475 |
38971.44 |
0.6667 |
30657.53 |
0.625 |
28740.00 |
|
2 |
Running cost |
-126,843 |
175,450 |
48,607 |
0.7182 |
34909.60 |
0.4444 |
21600.99 |
0.3906 |
18985.93 |
|
3 |
Running cost |
-129,380 |
180,714 |
51,334 |
0.6086 |
31241.70 |
0.2963 |
15210.18 |
0.2441 |
12530.56 |
|
4 |
Running cost |
-131,968 |
186,135 |
54,168 |
0.5158 |
27939.61 |
0.1975 |
10698.09 |
0.1526 |
8265.97 |
|
5 |
Running cost |
-134,607 |
191,719 |
57,112 |
0.4371 |
24963.76 |
0.1317 |
7521.68 |
0.0954 |
5448.51 |
|
6 |
Running cost |
-137,299 |
197,471 |
60,172 |
0.3704 |
22287.59 |
0.0878 |
5283.07 |
0.0596 |
3586.23 |
|
7 |
Running cost |
-140,045 |
203,395 |
63,350 |
0.3139 |
19885.51 |
0.0585 |
3705.96 |
0.0373 |
2362.95 |
|
8 |
Running cost |
-142,846 |
209,497 |
66,651 |
0.266 |
17729.10 |
0.039 |
2599.38 |
0.0233 |
1552.96 |
|
9 |
Running cost |
-145,703 |
215,782 |
70,079 |
0.2255 |
15802.76 |
0.026 |
1822.05 |
0.0146 |
1023.15 |
|
10 |
Running cost |
-148,617 |
222,255 |
20,000 |
93,638 |
0.1911 |
17894.25 |
0.0173 |
1619.94 |
0.00909 |
851.17 |
NPV = |
151625.32 |
NPV = |
718.87492 |
NPV = |
-16652.6 |
||||||
Total |
1,461,664 |
1,952,757 |
So @ i = 50% , PV = 718.87$
& @ i = 60% , PV = - 16652.6$
So the internal rate of return will be between 50% and 60% , using Interpolation IRR = 50.41%
Using IRR Excel command for estimating the IRR value , IRR = 50.353%
I have cheked your calculations on excel and they are spot on, you calculations are correct.
I am attaching my excel for yoyr reference.