You are scheduled to receive annual payments of $9,600 for each of the next 24 years. The discount rate is 8.0 percent. What is the difference in the present value if you receive these payments at the beginning of each year rather than at the end of each year?
$9,600.00
$10,368.00
$8,554.57
$9,279.36
$8,086.09
Since payback period is higher than required therefore project should be rejected | ||||
Correct answer is option = Reject | ||||
present value if payment received at the end | ||||
We have to use financial calculator to solve this | ||||
put in calculator | ||||
FV | 0 | |||
PMT | -9600 | |||
I | 8% | |||
N | 24 | |||
compute PV | $101,076.08 | |||
present value if payment received at the Beginning | ||||
We have to use financial calculator to solve this | ||||
put in calculator, set the calculator at BEGIN mode | ||||
FV | 0 | |||
PMT | -9600 | |||
I | 8% | |||
N | 24 | |||
compute PV | $109,162.17 | |||
Difference in value = | $8,086.09 | |||
109162.17-101076.08 | ||||
answer = | $8,086.09 |